Hi, i've completed my underground drainage and about to start on the soil stack. I'm just wondering if there's a need (or requirement) for an access pipe near the base of the stack. I ask because the access chamber is less than 2m away so pipe could be accessed from there.

Thanks for your help.

Posted: Sat Dec 17, 2011 6:15 pm
by lutonlagerlout
we normally always have an access panel about 300mm up the stack, I know they are expensive but can save you a lot of grief down the line