Posted: Fri May 19, 2006 10:15 am
we have a front drive approx 120 sq meters,kind of double L shaped,and i am thinking of setting it out in 4 metre wide bays useing alternative color paviors bedded in concrete ,as bands running away from the house ,then screeding the sand between theses bands and laying and finishing each sectionat a time,because i can`t finish the job in just a couple of days,only working weekendsand have big parking problems on the road outside,this way,as i finish a section,the family can drive on the finished sections straight away,my question is,do you think the paving bedded on the sand will settle a bit lower than the bands bedded on concreteafter a few months.?
Any help mnch apprechated
Any help mnch apprechated