Spongy sub-base

Other groundworks tasks, such as roads and footpaths, terracing, fencing, foundations, walls and brickwork, tools and plant.
Post Reply
Ruatha
Posts: 2
Joined: Sat Nov 27, 2010 5:19 pm
Location: Scotland

Post: # 56408Post Ruatha

Hi
I have started backfilling my porch foundations which are 3 courses of blockwork high.
I have backfilled the area around the blocks to the same level as the stable ground with the original gravel/sandstone (no soil)and given it a good run over with the wacker.
Now I have added 150mm of MOT Type 1 and given that a good wacking.
I now have some "spongy" areas which bounce when you walk on them.
The next layer is the DPM, Mesh rebar and 100mm concrete slab.
I am not happy putting the slab on top of something that is already spongy.

I guess I have 2 options - dig out to solid ground and then backfill and wack it again OR keep adding the hard core in the spongy areas and wack until it stops being spongy.

What would be your advice?

Thanks

dig dug dan
Posts: 2504
Joined: Thu Jul 10, 2003 10:20 pm
Location: hemel hempstead,herts. 01442 212315

Post: # 56413Post dig dug dan

you need to remove the subbase back to soil and add a layer of terram (which is a fabric membrane), then add the subbase.
This should eliminate the problem
Dan the Crusher Man
01442 212315
www.crusherhire.co.uk
"a satisfied customer? we should have them stuffed!"

Dave_L
Site Admin
Posts: 4732
Joined: Fri Jul 28, 2006 8:47 pm
Location: Somerset
Contact:

Post: # 56416Post Dave_L

I'd remove the original gravel/sandstone too if there was any doubt as to its suitability/condition.
RW Gale Ltd - Civils & Surfacing Contractors based in Somerset

See what we get up to Our Facebook page

Ruatha
Posts: 2
Joined: Sat Nov 27, 2010 5:19 pm
Location: Scotland

Post: # 56421Post Ruatha

Thanks for the help.
I decided to dig it out and refill with hard core.
Hopefully it will be more stable when I have it finished.