Question
-
- Posts: 1990
- Joined: Sun Mar 25, 2007 10:49 pm
- Location: N/Ireland
Here's one for you. Is it normal practise for the cleaning of the site and tools etc at the end of the day to be included as partof the working day and as such the client gets billed for it when you're on an hourly rate. Reason I ask is that a debtor is trying to pay me less than I've billed him and this is his excuse. On average it takes approx 30mins and we spent 17 days with 5 men so he's looking for a few quid. I tried ti get him on a fixed price but he insistedon hourly. He says it's standard practice in England where hisbuilding firm is from. I reckon it's a load of balls never heard of it as the dirt on tools and site is work related and has to be sorted by knock off.
Can't see it from my house
-
- Posts: 1951
- Joined: Sat Dec 06, 2008 10:28 pm
- Location: Preston, Lancashire
Its not standard practise with us, i agree with you, the cleaning of the site and equipment is part of a days work and should be billed accordingly.
I have seen some sites that are run by much larger national firms, were the lads jus arse about for the last half hour, if i were i paying customer id be bringing that to the attention of the gaffer!
I have seen some sites that are run by much larger national firms, were the lads jus arse about for the last half hour, if i were i paying customer id be bringing that to the attention of the gaffer!
-
- Site Admin
- Posts: 15184
- Joined: Fri Aug 04, 2006 12:20 am
- Location: bedfordshire
-
- Posts: 1951
- Joined: Sat Dec 06, 2008 10:28 pm
- Location: Preston, Lancashire
-
- Site Admin
- Posts: 4420
- Joined: Sat Aug 09, 2008 3:55 pm
- Location: high peak
- Contact:
yep we knock off at 4.30 so hopefully gate locked and out of there by 4.35.
its all part of the job to clean down and wash out.
although did a 12 hour day today, my 66 year old foreman and i poured 50m3 of c35 concrete, pumped in but had to finish tying the steel this morning but working for yourself is different. we finished about 5.30 is with clean down and lock up.
its all part of the job to clean down and wash out.
although did a 12 hour day today, my 66 year old foreman and i poured 50m3 of c35 concrete, pumped in but had to finish tying the steel this morning but working for yourself is different. we finished about 5.30 is with clean down and lock up.
Giles
Groundworks and Equestrian specialists, prestige new builds and sports pitches. High Peak, Cheshire, South Yorkshire area.
http://www.gbgroundworks.com
Groundworks and Equestrian specialists, prestige new builds and sports pitches. High Peak, Cheshire, South Yorkshire area.
http://www.gbgroundworks.com
-
- Posts: 83
- Joined: Tue Feb 10, 2009 4:50 pm
- Location: blackpool
reckon to many people employed thinking of ways to save money regardless to who they upset. most of them never got mud anywhere near there pointy shoes there the ones who need all the safety gear when on site! as for customers... well i think all these programs on telly highlighting dodgy builders do more harm than good, educating them how to be suspiciuos of everyone and winge about everything!
-
- Site Admin
- Posts: 1854
- Joined: Tue Aug 19, 2008 7:03 pm
- Location: kings lynn norfolk
- Contact:
As you are on daywork being paid to use tools and make mess,you expect to be paid to clean up and put away,why would you clean tools in your own time, :laugh:
in 91-92 i worked for fairclough civils , now known as amec i was on the books and we was allowed 10 mins at end off day on full pay to wash up and put tools away, take boots off if wet day,i belive this guy is taking the you know what
in 91-92 i worked for fairclough civils , now known as amec i was on the books and we was allowed 10 mins at end off day on full pay to wash up and put tools away, take boots off if wet day,i belive this guy is taking the you know what
paving, mini-crusher, mini-digger hire and groundwork
http://mshpaving.co.uk
http://mshpaving.co.uk
-
- Site Admin
- Posts: 4713
- Joined: Mon Jun 26, 2006 11:01 am
- Location: eastbourne
the cleaning of tools and work area are an ongoing part of the working day. clean as you go. the last half hour or so is usually dedicated to good housekeeping, putting up fencing, covering holes and cleaning tools etc. we have a rule on our sites called "take 5"
at a designated time ( 12.00 oclock ) an air horn sounds, every one stops work and for five minutes we check our work area, tidy up and get rid off rubbish until the horn sounds again. good housekeeping and making sure tools are not only cleaned but also checked for damage is very important. :;):
at a designated time ( 12.00 oclock ) an air horn sounds, every one stops work and for five minutes we check our work area, tidy up and get rid off rubbish until the horn sounds again. good housekeeping and making sure tools are not only cleaned but also checked for damage is very important. :;):
sean
-
- Posts: 84
- Joined: Sun Mar 02, 2008 7:51 pm
- Location: Canterbury, Kent
you could always smile and nod, yessir nosir three bags full sir till the end of the job...
...and then present him with a bill for some nice new trowels, floats shovels etc...make sure they're marshalltown, WHS etc :p
Might even be worthwhile trying to price bits and bobs like that into good sized jobs before you start, even if its stuff like plastic floats, string lines, pencils, it all adds up.
With regards to washing up times some people (Normally machine drivers IME) get very sniffy about knocking off times for breakfast or at the end of the day, sometimes suspicioulsy close to taking the pi55.
When it comes down to it your tools are your livelihood, perhaps the client in his ivory tower does not understand how many wives, children ferrets etc you have to feed and clothe.
...and then present him with a bill for some nice new trowels, floats shovels etc...make sure they're marshalltown, WHS etc :p
Might even be worthwhile trying to price bits and bobs like that into good sized jobs before you start, even if its stuff like plastic floats, string lines, pencils, it all adds up.
With regards to washing up times some people (Normally machine drivers IME) get very sniffy about knocking off times for breakfast or at the end of the day, sometimes suspicioulsy close to taking the pi55.
When it comes down to it your tools are your livelihood, perhaps the client in his ivory tower does not understand how many wives, children ferrets etc you have to feed and clothe.
S.P. HOLMES GROUNDWORKS
www.facebook.com/holmesgroundworks
www.facebook.com/holmesgroundworks
-
- Site Admin
- Posts: 4713
- Joined: Mon Jun 26, 2006 11:01 am
- Location: eastbourne
-
- Site Admin
- Posts: 1854
- Joined: Tue Aug 19, 2008 7:03 pm
- Location: kings lynn norfolk
- Contact:
I hate cheap and nasty tools,always buy the best i can afford never market junk,quality names only MSH
paving, mini-crusher, mini-digger hire and groundwork
http://mshpaving.co.uk
http://mshpaving.co.uk
-
- Site Admin
- Posts: 15184
- Joined: Fri Aug 04, 2006 12:20 am
- Location: bedfordshire
-
- Site Admin
- Posts: 4713
- Joined: Mon Jun 26, 2006 11:01 am
- Location: eastbourne
-
- Posts: 84
- Joined: Sun Mar 02, 2008 7:51 pm
- Location: Canterbury, Kent
Haha worldwide tools yes sean either them or "globemaster" with the plastic yellow handles
knips that don't nip
screwdrivers that don't screw
floats held together with fairy dust instead of rivets
and some nice new string lines...you have a choice of either bent or birdsnest :p
knips that don't nip
screwdrivers that don't screw
floats held together with fairy dust instead of rivets
and some nice new string lines...you have a choice of either bent or birdsnest :p
S.P. HOLMES GROUNDWORKS
www.facebook.com/holmesgroundworks
www.facebook.com/holmesgroundworks
-
- Posts: 84
- Joined: Sun Mar 02, 2008 7:51 pm
- Location: Canterbury, Kent
because us brits can use anything and still turn out quality work
bricking up using a shovel and a bit of rubber hose to joint...
benching manholes with coke cans and milk bottles
what is it they say ..."Necessity is the mother of invention"
:laugh: