Brick chimney - Building an external fire & chimney
-
- Posts: 3
- Joined: Wed Aug 30, 2006 9:48 pm
- Location: Bolton
Hi, can anyone please offer any guidance or assistance with the following?
I am looking to build / have built a Brick Fireplace and Chimney in the garden.
The grate will be 36" wide and therefore am looking at a 4 foot opening.
I am not sure of the internal construction of the brickwork to support the liner & stack which I feel will need to be around 10 Feet high to facilitate draw.
Is there a plan available for the internal brickwork construction?
(Do I need to go higher than 10 feet)? is there a calculation for the opening volume V's chimney height to ensure draw is achieved?
In addition I require the chimney to be twisted. I am told there is a template for this? Where can I get one and how is the twisted effect done.
I am not a builder as you may have guessed by now, just enthusiastic to have a go!!! Or,
Does anyone out there carry out this type of work?
Thanks for reading.
Chris
I am looking to build / have built a Brick Fireplace and Chimney in the garden.
The grate will be 36" wide and therefore am looking at a 4 foot opening.
I am not sure of the internal construction of the brickwork to support the liner & stack which I feel will need to be around 10 Feet high to facilitate draw.
Is there a plan available for the internal brickwork construction?
(Do I need to go higher than 10 feet)? is there a calculation for the opening volume V's chimney height to ensure draw is achieved?
In addition I require the chimney to be twisted. I am told there is a template for this? Where can I get one and how is the twisted effect done.
I am not a builder as you may have guessed by now, just enthusiastic to have a go!!! Or,
Does anyone out there carry out this type of work?
Thanks for reading.
Chris
CL
-
- Site Admin
- Posts: 15184
- Joined: Fri Aug 04, 2006 12:20 am
- Location: bedfordshire
your on the wrong site mate
this is pavingexpert.com
but as i build as well ,i will give you a tip
if you have never laid bricks before get a brickie in,it takes 4000 hrs of practise to lay bricks to a standard,i have never seen a diyer do a half decent job yet
the twisted effect i have done many times but again it is advanced brickwork,you will not be able to do it mate.sorry
as for the chimney normally it as to be 600mm above the nearest roofline,but the main thing is ,it has a draw i.e. the smoke gets sucked up it
hope this helps
tony
this is pavingexpert.com
but as i build as well ,i will give you a tip
if you have never laid bricks before get a brickie in,it takes 4000 hrs of practise to lay bricks to a standard,i have never seen a diyer do a half decent job yet
the twisted effect i have done many times but again it is advanced brickwork,you will not be able to do it mate.sorry
as for the chimney normally it as to be 600mm above the nearest roofline,but the main thing is ,it has a draw i.e. the smoke gets sucked up it
hope this helps
tony
-
- Posts: 106
- Joined: Mon Jul 07, 2003 3:07 pm
-
- Posts: 3
- Joined: Wed Aug 30, 2006 9:48 pm
- Location: Bolton
Thanks for thae reply. (Both of you).
Carl, you seem to have done an excellent job and you say you aren't a brickie !
Well, I agree with you, that blows the 4,000 hours practice theory out of the water.
The job looks better than some of the buildings I have seen erected on some new build sites which are constructed by brickies.
Well done !
However, does anyone out there know wher I can get a template as requested for the twisted brick.
I will be able to do it, maybe not as fast !
Thanks !
Carl, you seem to have done an excellent job and you say you aren't a brickie !
Well, I agree with you, that blows the 4,000 hours practice theory out of the water.
The job looks better than some of the buildings I have seen erected on some new build sites which are constructed by brickies.
Well done !
However, does anyone out there know wher I can get a template as requested for the twisted brick.
I will be able to do it, maybe not as fast !
Thanks !
CL
-
- Posts: 308
- Joined: Sat May 27, 2006 9:19 pm
- Location: cheadle uk
-
- Site Admin
- Posts: 4732
- Joined: Fri Jul 28, 2006 8:47 pm
- Location: Somerset
- Contact:
Nice job!!
The "joints" are ventilation slots aren't they?
The "joints" are ventilation slots aren't they?
RW Gale Ltd - Civils & Surfacing Contractors based in Somerset
See what we get up to Our Facebook page
See what we get up to Our Facebook page
-
- Posts: 934
- Joined: Tue Nov 01, 2005 10:57 pm
- Location: Buckinghamshire
- Contact:
-
- Site Admin
- Posts: 15184
- Joined: Fri Aug 04, 2006 12:20 am
- Location: bedfordshire
carl very nice bit of bwk,but i would guess you have been on the building all your working???
i know roofers and plasterers that can lay bricks ,but i am talking about a desk jockey starting from scratch
the 4000 hrs is roughly the amount of practise an apprentice gets in 4 years,i have started flint knapping lately and having been in the buildings for 20 years obviously helps
right spiral piers
concrete an 8 ft scaffold tube in vertically at the centre of the chimney
cut a peice of ply 450 by 450 dead square
cut a 50mm hole in the centre of the ply
place the ply over the scaff tube and use as your profile moving it approx 10mm at a time for a nice spiral effect
i will post a picture of some spiral piers i have doen recently tommorrow
cheers fellas
tony
i know roofers and plasterers that can lay bricks ,but i am talking about a desk jockey starting from scratch
the 4000 hrs is roughly the amount of practise an apprentice gets in 4 years,i have started flint knapping lately and having been in the buildings for 20 years obviously helps
right spiral piers
concrete an 8 ft scaffold tube in vertically at the centre of the chimney
cut a peice of ply 450 by 450 dead square
cut a 50mm hole in the centre of the ply
place the ply over the scaff tube and use as your profile moving it approx 10mm at a time for a nice spiral effect
i will post a picture of some spiral piers i have doen recently tommorrow
cheers fellas
tony
-
- Posts: 106
- Joined: Mon Jul 07, 2003 3:07 pm
Suggers wins the prize.
The holes have now been pointed.
Also, I am a desk jockey , started from scratch. I am a television engineer by trade and I built the garage on my own in my spare time. The only thing that I used that a proper bricke may not were building profiles at the four corners. I guess these would not help build a twisted chimney though.
Chris7 , Hope you will show us a picture of the fininshed chimney.
Cheers Carl
The holes have now been pointed.
Also, I am a desk jockey , started from scratch. I am a television engineer by trade and I built the garage on my own in my spare time. The only thing that I used that a proper bricke may not were building profiles at the four corners. I guess these would not help build a twisted chimney though.
Chris7 , Hope you will show us a picture of the fininshed chimney.
Cheers Carl
-
- Site Admin
- Posts: 15184
- Joined: Fri Aug 04, 2006 12:20 am
- Location: bedfordshire
-
- Posts: 106
- Joined: Mon Jul 07, 2003 3:07 pm
I started my 40 square meter garage in Febuary. I work full time so some weeks I have done notthing on the garage at all. Also , when I said i did everything my self, I knocked up all the mortar, moved all the bricks and blocks my self and even built my own scafolding.
I can now lay about 400 facing bricks in a day , but again, being my own labourer slows me down. I could only do about 200 when I first started. I would like to use a labourer and see how many I could lay in a day.
One day the wife helped get the mix from the mixer to my spot. I could then lay so much faster she could not keep up.
Practice does make you get quicker but at the start , I was paranoid about geting each brick perfect. I can now do it without thinking.
I still have a lot to learn, but due to there being a current redundence cull at work, I was thinking about becoming a builder beacause the televiosn game is dying with cheap TV's
I was worried about the building control at the start, but as long as I did my research and kept everything within regs, each inspection so far as been a doddle.
Hope that continues.....
:;):
Cheers Carl
I can now lay about 400 facing bricks in a day , but again, being my own labourer slows me down. I could only do about 200 when I first started. I would like to use a labourer and see how many I could lay in a day.
One day the wife helped get the mix from the mixer to my spot. I could then lay so much faster she could not keep up.
Practice does make you get quicker but at the start , I was paranoid about geting each brick perfect. I can now do it without thinking.
I still have a lot to learn, but due to there being a current redundence cull at work, I was thinking about becoming a builder beacause the televiosn game is dying with cheap TV's
I was worried about the building control at the start, but as long as I did my research and kept everything within regs, each inspection so far as been a doddle.
Hope that continues.....
:;):
Cheers Carl