Can anyone help me out
I’m looking to use a rotary level
On the plan you can see +10.00 at the top of the plan
I’m trying to work out how I can reach this on a staff and all the other heights on the drawing
We are wanting to dig the site area out which will be +5.00
I think I could pretty much get ther by using the +6390 and digging down 1390 and come off level by this, but I’d like to know how to use a level
Also wher I should position the laser in the first place
Can anyone advise please
Plan
Use a rotary level - Help finding levels
-
- Posts: 889
- Joined: Fri Jan 18, 2008 9:32 pm
- Location: cheshire
-
- Posts: 5
- Joined: Sun Oct 29, 2017 9:21 pm
- Location: Kent
-
- Posts: 889
- Joined: Fri Jan 18, 2008 9:32 pm
- Location: cheshire
-
- Site Admin
- Posts: 8346
- Joined: Mon Jul 05, 2004 7:27 pm
- Location: Warrington, People's Republic of South Lancashire
- Contact:
Set up your level in a position that can clearly see all relevant level points on the site, or as many as is possible. I’d suggest somewhere a metre or so from the top right corner of the house, and set as high as you can comfortable reach, even if stood on a box, say 2m (ish) above GL.
Take a staff reading at your datum point. I don’t know what points are in existence, but, again for argument’s sake, let’s assume the footpath at the front of the property is extant, and has the level shown on your plan : 3190
Knock in a masonry nail at this point so you can find it again if necessary.
Let’s say, for argument’s sake, that the reading from the staff on this datum point says 1950
You know the plan has this point as 3190, but your staff says 1950, so you would need to add 1240 to the staff reading to get the same result.
Now, if you move the staff to a peg marking, say, the lower RH corner of the building, you know that the level here is supposed to be 5000 but you also know that your level is giving readings at 1240 below the plan levels, so you need to set a level at this point/peg that is 5000 minus 1240 = 3760
When you get a staff reading of 3760, you know that, in relation to your original datum point on the footpath, this point/peg is 1810 higher (5000 – 3910)
Your staff reading at datum was 1950. Add the 1810 rise that is required: 1950 + 1810 = 3760. You need to set the peg to a level read from the staff of 3760
Now, you can use the same technique to establish levels elsewhere on the site.
Does this make sense?
Take a staff reading at your datum point. I don’t know what points are in existence, but, again for argument’s sake, let’s assume the footpath at the front of the property is extant, and has the level shown on your plan : 3190
Knock in a masonry nail at this point so you can find it again if necessary.
Let’s say, for argument’s sake, that the reading from the staff on this datum point says 1950
You know the plan has this point as 3190, but your staff says 1950, so you would need to add 1240 to the staff reading to get the same result.
Now, if you move the staff to a peg marking, say, the lower RH corner of the building, you know that the level here is supposed to be 5000 but you also know that your level is giving readings at 1240 below the plan levels, so you need to set a level at this point/peg that is 5000 minus 1240 = 3760
When you get a staff reading of 3760, you know that, in relation to your original datum point on the footpath, this point/peg is 1810 higher (5000 – 3910)
Your staff reading at datum was 1950. Add the 1810 rise that is required: 1950 + 1810 = 3760. You need to set the peg to a level read from the staff of 3760
Now, you can use the same technique to establish levels elsewhere on the site.
Does this make sense?