Connecting to existing shallow access chamber
-
- Posts: 4
- Joined: Tue Nov 24, 2015 8:43 am
- Location: UK
Hi,
A quick enquiry about connecting a new foul drain to an existing system.
I have a shallow access chamber in plastic - see attached image. There are three inlets and one outlet. Currently the inlet that it directly in line with the outlet is used for foul, one of the other two is used for sink and bath waste, ie no solids.
I need to connect a new foul to the other inlet, ie from a WC some way off from the drain.
I understand that I'll need building reg permission etc, but is this likely to work or will I need to change the chamber, perhaps replacing it with an unequal one with side inlet raised above the main inlet?
Is this equal chamber designed to take foul solids from all three inlets? Looking at the design, I have concern that solids and paper may get snagged, or am I being overly concerned?
Thanks in advance.
A quick enquiry about connecting a new foul drain to an existing system.
I have a shallow access chamber in plastic - see attached image. There are three inlets and one outlet. Currently the inlet that it directly in line with the outlet is used for foul, one of the other two is used for sink and bath waste, ie no solids.
I need to connect a new foul to the other inlet, ie from a WC some way off from the drain.
I understand that I'll need building reg permission etc, but is this likely to work or will I need to change the chamber, perhaps replacing it with an unequal one with side inlet raised above the main inlet?
Is this equal chamber designed to take foul solids from all three inlets? Looking at the design, I have concern that solids and paper may get snagged, or am I being overly concerned?
Thanks in advance.
-
- Site Admin
- Posts: 4713
- Joined: Mon Jun 26, 2006 11:01 am
- Location: eastbourne
-
- Site Admin
- Posts: 4713
- Joined: Mon Jun 26, 2006 11:01 am
- Location: eastbourne
-
- Site Admin
- Posts: 4713
- Joined: Mon Jun 26, 2006 11:01 am
- Location: eastbourne
-
- Site Admin
- Posts: 15184
- Joined: Fri Aug 04, 2006 12:20 am
- Location: bedfordshire
-
- Site Admin
- Posts: 4713
- Joined: Mon Jun 26, 2006 11:01 am
- Location: eastbourne
The main concern with a chamber is that you maintain the flow on the lowest inlet, it must be used. If you have stepped channels and slippers you can go into any with foul as long as your using the lowest invert also, you may have to orientate the chamber using easy bends. Building control like foul to be rodable both ways especially with a toilet added, you might get away with it if it's just sink waste, therefore a y on a wc may be unlikey to be passed off. Also depends on you BC guy.
sean
-
- Posts: 4
- Joined: Tue Nov 24, 2015 8:43 am
- Location: UK
Thanks for all of this info - have learned plenty.
I've since sourced a better access chamber which appears to take foul on any of the three inlets. The direct-through inlet is approx 4 inches lower than the two side inlets, so through-flow should be much more reliable.
This also comes with flexible connections on all inlets which allows 10° movement in any direction - that'll help hugely with installation as existing angles are hard to determine.
The digging starts this weekend ...
Thanks again for advice.
I've since sourced a better access chamber which appears to take foul on any of the three inlets. The direct-through inlet is approx 4 inches lower than the two side inlets, so through-flow should be much more reliable.
This also comes with flexible connections on all inlets which allows 10° movement in any direction - that'll help hugely with installation as existing angles are hard to determine.
The digging starts this weekend ...
Thanks again for advice.
-
- Site Admin
- Posts: 4713
- Joined: Mon Jun 26, 2006 11:01 am
- Location: eastbourne
-
- Posts: 4
- Joined: Tue Nov 24, 2015 8:43 am
- Location: UK
Thanks for this.
We have no choice in terms of replacing the existing manhole - it's knackered and the two inlets are cracked also. The main clay outlet from existing is also broken and requires rodding every few weeks. One of the inlets also slopes upwards before reaching the manhole, and this needs fixing too. All a bit of a mess, so all needs replacing.
The new access chamber will need to be installed at a slightly lower level than existing to accommodate the differences in inlet height and incorrect fall on one inlet. There is room to do this, as the outlet run goes some 20 metres with good fall and this will be changed for plastic also as it currently blocks - I'll probably need to lose three inches height on the total run.
Three inches on a 20m run with good fall and new plastic should be okay ..... fingers and other parts crossed ...
We have no choice in terms of replacing the existing manhole - it's knackered and the two inlets are cracked also. The main clay outlet from existing is also broken and requires rodding every few weeks. One of the inlets also slopes upwards before reaching the manhole, and this needs fixing too. All a bit of a mess, so all needs replacing.
The new access chamber will need to be installed at a slightly lower level than existing to accommodate the differences in inlet height and incorrect fall on one inlet. There is room to do this, as the outlet run goes some 20 metres with good fall and this will be changed for plastic also as it currently blocks - I'll probably need to lose three inches height on the total run.
Three inches on a 20m run with good fall and new plastic should be okay ..... fingers and other parts crossed ...
-
- Site Admin
- Posts: 4713
- Joined: Mon Jun 26, 2006 11:01 am
- Location: eastbourne