How long to leave terrace footing before building - Curing time for 4 inch concrete footing

Other groundworks tasks, such as roads and footpaths, terracing, fencing, foundations, walls and brickwork, tools and plant.
Post Reply
Simo
Posts: 2
Joined: Mon Mar 16, 2015 1:06 pm
Location: London

Post: # 103169Post Simo

Hi
I'm building a 2.5ft high dry stacked terracing wall in the garden using some old reclaimed paving slabs as outlined here:

terracing

I've laid a 4 inch concrete footing below ground level and wonder how long I should leave it to cure before starting to build up the courses of slabs ?

Also - I haven't bedded the first course of slabs into the footing as illustrated, but I have created a backsloping profile in it so that the stacked slabs should create the batter as I build up. Does that sound reasonable ?

Thanks

P.s. Many thanks for putting this site together - it's been a constant source of reference as I've been re-landscaping the garden !
Simo

seanandruby
Site Admin
Posts: 4713
Joined: Mon Jun 26, 2006 11:01 am
Location: eastbourne

Post: # 103172Post seanandruby

You could start almost immediatly as i'm sure the progress will be slow.
Having said that i'd give it 24/48 hours to go off a bit.
sean