pavingexpert.com aj mccormack and son

Block Paving - Page 09
The Brew Cabin
block paving
archive

spacer

 ruler
spacer spacer spacer spacer spacer spacer
Forum Question Concrete for hardcore base? - BillieJNR - May 19th 2003
I want to slightly alter the shape of my drive. This means paving an extra strip only 6-12" wide. As it doesn't seem practical to get a wacker plate into such a narrow strip, is it worth using concrete for the base? I'm assuming concrete would consolidate much easier than dry limestone?
forum answer Tony McCormack
May 19th 2003
You could do that, I suppose. There's not much point in bringing in a lot of kit to pave such a small strip, so a concrete bed/base would be the logical method. You could bed the blocks directly onto 100mm or so of a C20 equivalent concrete, and haunch the outer edge with the same.
BillieJNR
May 19th 2003
I had planned to use concrete as an alternative to hardcore and put sand over the top. All concrete sounds easier, except that I'll have to get it right pretty much first time! It's for a drive and there's a risk of getting a HGV on the new paving. I've excavated 150mm. Will the all concrete method survive an occaisional HGV? Thanks very much for your advice.
Tony McCormack
May 19th 2003
HGV?? For pavements carrying such heavy loads, the usual method is to use 80mm thick blocks and lay them on a 35-50mm sand bed over a 150mm concrete base, but, as yours is so narrow and at the edge of the pavemnt, laying on sand is not feasible, so that's why I suggest laying directly onto concrete. However, the depth of the concrete should be at least 150mm, given the loads you anticipate, and the haunching will need to be very strong, at least 150mm wide.

What's the construction of the existing driveway?

BillieJNR
May 19th 2003
Existing construction is standard: Rococo Cobble Setts over sand and hardcore. Quite a decent job, done by the buliders, Seddons. HGV's will be whatever delivery vehicles have to come to us. No problems so far, including large brick wagon on a couple of occasions and many sixteen tonners
DavidW
May 28th 2003
Please excuse me for latching on to someone else's query, but my D-I-Y question is related.

I want to extend my existing driveway, currently Marshall's Driveline 60. I would use their Driveline 50 and appreciate that there may be some colour difference.

The easiest way seemed to be to lay the new blocks directly on top of an existing 150mm thick concrete slab (40 sq metres). To keep the levels right for drainage, this would mean setting them on a 15mm - 30mm concrete bed on top of the slab rather than on compacted sand. I asked Marshall's advice and they strongly recommended against this, saying that I must have at least a 35mm sand bed on top of the concrete slab. I didn't ask why.

I don't really want to break up and dispose of such a big area of concrete. The drive extension is most unlikely to be used for anything other than cars. Is it really necessary to lay on compacted sand?

Tony McCormack
May 28th 2003
The reason why the blocks should be laid on a minimum 35mm bed of compacted grit sand is that they have been specifically developed for flexible paving and laying them onto a rigid bed could cause problems. Obviously, it could all go swimmingly well, but if Marshalls were to suggest that such a laying method was suitable, they open themselves to all sorts of legal problems.

I suggested direct bedding to the previous query because it is such a relatively small area - not much more than an extra soldier course, but for larger areas, I have to agree with Marshalls and say the blocks really should be laid on a sand bed over a suitable base or sub-base. You could lay the blocks on sand over the existing concrete (see the Laying over an Existing Base page) if the situation is suitable, which would do away with the problem of breaking up all that concrete, but have a read of that page first, and see if it's possible.

DavidW
May 29th 2003
Tony, thanks very much for your prompt and helpful reply. You should be extremely proud of your website & forum and the help they have given so freely to so many people.

I can now see that laying over the existing concrete base is not the right way so I will be hiring a breaker and skip for a few days!

 ruler
Forum Question Driveway Entrance - What size? - Barry England - May 19th 2003
I cannot decide if I should widen the entrance to my drive way when I have a block paved driveway laid. Current width if 1.7m which is a little tight when one car is already in the drive & we need to pass that car to park the 2nd. Is there a recommend / suggested width?

Thanks for the help.

forum answer Tony McCormack
May 19th 2003
The minimum for a typical car is 2.1m, but that is quite tight, allowing only 150mm of clearance either side. Most driveways on new houses are laid to a minimum 2.4m width, and I would take that as a minimum opening width for comfort. However, if you're having work done, then you might as well make life as simple as possible and opt for a 3m opening, it possible, as that gives a good 600mm (2 feet in old money) of clearance on either side of a typical car.
 ruler
Forum Question Stretcher Bond or Herringbone - Peter P - May 26th 2003
I've read on your site that herringbone is the preferred pattern for driveways. Both myself and my wife prefer the stretcher bond pattern. Is this a definite no no or is it just slightly weaker in strength than the herringbone pattern? We will be using 50mm deep block paving and we only have the one car. The driveway won't be subject to heavy daily use. Many thanks for your help.
forum answer Tony McCormack
May 27th 2003
Herringbone is preferred because it gives a full interlock - that is, the pattern resists being shifted either logitudinally or transversely. However, as it's your own driveway, you can have whatever pattern your heart desires, including stretcher bond.

The only word of advice I'd offer is that you make sure the bond runs transversely (pavior-speak for the bricks to run across the drive rather than 'up and down', which is referred to as longitudinal). Laying transversely is more pleasing to the eye, is structurally stonger, and has the added benefit of hiding any slight pattern creep for casual passers-by. smile

 ruler
Forum Question Mortar or Sand bedding for USA? - D Lopez - May 29th 2003
I have a new home, with no driveway at all yet. I want to install pavers and would like to know if it is best to install them on crushed rock & sand or in mortar on top of a lowered cement driveway?
Thanks!
forum answer Tony McCormack
May 30th 2003
Over here, on these soggy but pleasant islands, the most common construction is the flexible bedding, what you describe as 'crushed rock and sand', and I know the same construction is used in other parts of the world, even those experiencing problems with frost heave. Rigid bedding (laying on mortar over a concrete base) is much harder work, more expensive and requires bricks specifically manufactured for that type of construction and so tends not to be used for residential driveways unless there is a specific reason to do so.

I'd hazard an educated guess and say that flexible bedding is the way to go with your project.

D Lopez
May 30th 2003
Thanks, I'm in El Paso, Texas, USA. It is very hot & dry weather here. Would there be any advantage to setting the pavers in mortar?
Tony McCormack
Jun 1st 2003
None that I can think of, but you may be better off asking a US-based contractor. I've seen dozens of case studies of flexible paving in the US, including some in hot/dry areas, and there doesn't appear to be any problems.
 ruler
Forum Question Laying Driveline blocks radially - Radial Dave - May 30th 2003
I will be paving 30 m² of my front garden to park two cars. I want to start with a Driveline 50 circle pack and then use normal driveline blocks to keep building the circle larger. Will I get enough interlock on a 5° slope? Would I be better off keeping the outer bricks the same orientation as the inner bricks (i.e. lengthways along the radius) or turning them through 90° and having them lengthways around the circumference?
forum answer Tony McCormack
Jun 1st 2003
A circular layout generally gives sufficient interlock for a typical residential driveway.

How you choose to lay the additional circles is up to you. The first couple of courses may need some trimming to keep joints widths reasonable, but after that, the full blocks usually fit quite well.

Here's an image of your options....

driveline circle

...if you intend using the same colour, then laying the additional courses lengthways (as on the left hand side of the image) looks better to my eye, but if you plan to change colour, then laying the blocks widthways can help emphasise the change.

 ruler
Forum Question Kerb Edge or No Kerb Edge - A Cassidy - Jun 2nd 2003
I have a common drive way with a neighbour. They do not have block paving and we do. I have not had a kerb edge fitted to the common boundary and I am finding that a few edge blocks at the entrance to the drive are moving. Is this because I have no kerb (is a kerb a must) or is it more likley that the contractor did not concrete the edge blocks in correctly?
forum answer Tony McCormack
Jun 3rd 2003
A kerb is not essential, it is merely a decorative addition to block paving. What is essential is that the edge of the paving, whether it's a kerb or a plain soldier edging, absolutely must be laid on and haunched with concrete, or some other restraining device, to prevent the paving from spreading onto your neighbour's plot.

So, if a block pavement has a kerb, that can be concreted-in and used as the restraining edge, or, as is the case with your drive, the edge blocks should be concreted-in.

 ruler
Forum Question 50mm or 60mm? - Cott66 - Jun 6th 2003
What's the best for patios? 50 or 60 millimetre thick blocks? What is the main advantage?
forum answer Tony McCormack
Jun 6th 2003
For patios, the 50mm thick blocks are probably the better option, as they save you 10mm of excavation, they are fractionally cheaper, and they're easier to cut. The main advantage of the 60mm blocks is that they are BS6717 compliant and generally a better product for vehicular areas.
 ruler
Forum Question Paving into doorway - Cott66 - Jun 6th 2003
If the blocks run along house straight, then where the door is it goes in 150mm, do I keep it straight and fill in behind the blocks?
forum answer Tony McCormack
Jun 7th 2003
I'm not absolutely sure what you mean, but I think it's something like....

rebated soldier

....where the wall is rebated (stepped back) to accommodate the doorway, the soldier course should follow the brickwork, as shown in the right-hand image above, rather than be 'infilled' behind the soldier course, as shown in the left-hand image.

Is that what you meant?

Cott66
Jan 11th 2003
Yes, thank you.
 ruler
Forum Question Replacing bitmac with blocks - Pete T - Jun 9th 2003
Novice - first post.
Have read lots on your site and decided to DIY block paving drive (car use). However I struggle with the following:
I have an existing tarmac drive on what is probably a good sub base that has been laid for many years. I intend to remove the tarmac but would like to use the existing sub base. However the depth of the tarmac is far less than what will be the final depth of bedding layer plus blocks. This means that the drive will sit above the level of the footpath. I dont have a problem with a higher drive but....
My question is, what is the best way to create a slope between the drive and the footpath?
I will be using TopPave blocks and therefore a 'multi purpose kerb' with a sloping edge will be available. However I dont think the slope on the kerb will be enough for the transition.
Alternatively should I remove some of the sub base to create a gentle slope near the edge, say for the end metre or so? Will the reduced depth of sub base affect the load bearing efficiency of the drive? (Afraid I dont yet know the depth of the sub base.)
I don't favour an infill between the two as mentioned in other posts as this will look a botch job. Is there an alternative. Your thoughts would be appreciated.

Regards
Pete T

forum answer Suki
Jun 12th 2003
I would advise against this as tarmac drives very rarely have Class 1 MOT under them and if they have it almost certainly wont be 150mm of MOT. I have seen many diy jobs do what you are going to do, all have the same result - differential settlement and rutting in around 6 months of the drive going down which will really show up when it rains.

I would first take off some tarmac and have a dig down to see what the sub base consists of and how deep it is and then consider your options, but I imagine you will have to have it dug and done right at the end of the day. It's your house and you want it 100%. If however you go ahead and use the existing sub base you will probably have to opt for a sloping bullnose kerb edger and have maybe a small bump up onto the drive as I certainly would not entertain removing subbase at the entrance to a drive.

Good luck.

Pete T
Jun 12th 2003
Suki,
Thanks.
Looks as if I'll be doing a bit of 'digging' this weekend to examine the sub base....
Pete T
Tony McCormack
Jun 14th 2003
Have a look what the sub-base is like before finally deciding on a strategy. On some properties, the sub-base can be fine, and, if it's been down a good number of years, you have the added security of knowing that there's no settlement potential. Assuming you're only going to be using the driveway for cars and, at worst, light vans, then I'd suggest that, as long as you have a good 75mm minimum of sub-base, then it's a better idea to use that than to dig it all out and start again with 100-150mm of new sub-base material that will take years to become as well-consolidated as what you currently have.

For the transition between the driveway and the public footpath, your idea to use a kerb unit to form a short ramp is fine, or you could scrape away at the sub-base to create just enough depth to accommodate the new paving and a minimal bed of 30mm of sand. Personally, I like the idea of using the kerb units, and then, if you're still struggling for depth, use an extra-wide border course, perhaps even building in a pattern such as....

threshold

...just at the transition will help overcome the level difference.

Pete T
Jun 14th 2003
Tony,
Thanks for that advice. I didn't really want to dig all the sub base up only to put another, deeper one in. Hopefully the existing one will be over 75mm. The transition idea of an extra wide border is good, but I'll have a look at the depth first.

Must admit I feel more confident now.

Thanks
Pete T

 

Later...... I have 'dug a hole' in my drive. There are two layers of tarmac. (The drive was re surfaced some 10 years ago). The total depth of the tarmac is about 60mm . The depth of the sub base is about 100mm. By removing the tarmac and using 60mm blocks and about 40mm of bedding sand will mean a raised height of 40mm above current level. If I use a top pave multi purpose kerb this will give a slope reducing the height at the edge by 50% (30mm). ie 10mm above the current level. Therefore If I 'skim' the sub base (10mm) at the edge, the drive and footpath should end up level.

Finally should I have the existing sub base material checked to see if it is suitable. It has obviously settled and compacted over many years but I'm not sure if I can tell the difference between MOT1 and 2 (or any other material).

Pete T

Tony McCormack
Jun 18th 2003
It all sounds fine, Pete. The test to determine just what type of sub-base material you have, and how effective it is, would probably cost more than a new driveway, so don't worry about it. If it's been trafficked for the past 10 years and hasn't rutted or developed "elephant's footprints", it will be fine.

Once you've removed the bitmac, and skimmed-off as required to accommodate the paving at key points, you need to 're-grade' the sub-base, which simply means checking it all for level, skimming off any high spots and filling in any low spots or hollows with DTp1, and then compacting it all again. Although much of it will be firm and solid, the tarmac removal and subsequent tittivating will have loosened the sub-base in places, so it's best to reconsolidate the lot in one operation rather than do bits here and there.

Are you ok with your dpc levels?

Pete T
Jun 18th 2003
Thanks again.
re the DPC. The final level will be below the DPC by more than 100mm.

I plan to use Toppave Classico blocks which are not exactly rectangular (they have slightly curved sides) and therefore the gaps between the blocks is larger than normal. Toppave recommend using 'Classico Chippings' brushed in followed by the kiln dried sand. Have you (or anyone else) experienced any problems with these bricks?

Pete T

Tony McCormack
Jan 19th 2003
Is "more than 100mm" the same as "almost 150mm"? The Building regs require 150mm between any paved surface and the dpc, and this is the sort of thing that is picked on by a surveyor if you ever come to sell the property.

Anyway, Classico Blocks are fine and the Classico chippings are fine, too, if a little overpriced. For that reason, many installations of Classico disregard the chippings completely and use all sand joints with no apparent loss of pavement performance. smile

Pete T
Jun 20th 2003
Tony,
Thanks again.

The drive only extends about 600mm into the side of the house, at which point there is the front of the garage. The existing height of the drive is 100mm below DPC. The garage is linked to the neighbours house; the drive adjoining that by the same 600mm and 100mm DPC height. I wasn't aware of the 150mm rule (and presumably the contractor who laid the last tarmac didnt either...). Can I / should I put a short length of say damp proof membrane between the drive adjacent to the houses?

regards
Pete T

Tony McCormack
Jun 20th 2003
How much of the driveway (in linear metres) is in direct contact with the walls of the house/garage? If it's just a couple of metres or less, then don't worry about it, but if it's say, 3m or more, then have a look at a few of the ideas on the Dealing with DPCs page, which are more effective than simply laying a strip of DPC material.
Pete T
Jun 20th 2003
About 600mm in length in contact with the house so I' m not going to worry about it.
I will be starting work next w/e. Only a relatively small job (25 sq metres).

Pete T

 ruler
Forum Question Mowing strip bedding - Skippyatoz - Jun 11th 2003
Hi all -

I'm installing a mowing strip with edging in my front yard. I'm using 4" x 8" x 2 3/8" concrete bricks side-by-side for the mowing strip, and standing the same bricks on-end right behind the strip to use as edging.

I use a lawn tractor for mowing. I'm concerned that a sand bed won't be stout enough to take the weight of the mower, and will shift the bricks. I'd rather not resort to cementing it all because, well, it'd be a LOT of concrete!  This yard is about 30 by 60 feet.

I'm not afraid to do some digging though, and my idea is this - take the same approach as a pavior walkway and make a foundation of compacted gravel (2-4 inches), another few inches of bedding sand, and lay my bricks on that. Could it work?

I'm in western Washington State, USA, and the weather is approximately like that of England. Snow can happen but is not common, and we don't get deep freezes. My soil is pretty normal - it isn't sandy or clay-like.

- Neil

forum answer Suki
Jun 12th 2003
Depending on what type of sub grade you have, ie firm or soft, the best and quickest way would be to bed them into a 25-50mm concrete. Sorry about that if you want to dig down and fill with MOT and wacker that, then it would work but I would want around 100mm of MOT and 25mm of sharp. Seems a lot more harder work than the concrete option though.
Tony McCormack
Jun 14th 2003
Suki is right, again - laying the bricks on sand and a sub-base may well prevent them settling downwards, but it offers no protection against lateral movement, and so, I think you'd find the blocks slipping, gradually, out of alignment.

From a workload point of view, I'd guess that laying the blocks on, say 50-75mm (2-3 of your old-fashioned inches) of concrete, is actually less work than excavating for, laying and compacting a sub-base of 100mm and then repeating the process with the sand bedding.

 ruler
Forum Question Rubber Sole on a Wacker - Martin B - Jun 11th 2003
Is it advisable to use the rubber sole on a Wacker when bedding in the blocks? My worry is that not using one will lead to damage or scratching of the blocks.

Thanks for your help and such a great website.

Martin B

forum answer Suki
Jun 11th 2003
If you spread the kiln-dried sand around generously where you are about to wacker, then the kiln will cushion the plate from the blocks. I sand every job and wacker without a rubber plate and never have a problem. I only use the rubber on clays.
Tony Mcormack
Jun 14th 2003
Most concrete blocks don't ned the rubber mat fitting to the base of the vib plate, as they are tough enough to withstand a good rattling, and, with the tumbled types, even if there was a minor amount of damage, you'd never notice. The flexible bedding actually helps absorb the force of the vibration, and so the blocks are spared the worst effects of the plate compactor. Consequently, rigid-bedded blocks should not be vibrated once the bedding/jointing has cured.

Clay pavers are often considered to be more brittle than their concrete cousins, and so many contractors choose to use the rubber mat when consolidating, but it's not always necessary - as Suki says, a good, generous covering of the jointing sand can provide a sufficient degree of cushioning, and the only real danger of spalling clay pavers is when, because of the slight deformations that are inherent with any kiln-fired product, two adjacent bricks are in direct contact, and so rattle against each other. Because concrete pavers have a high level of dimensional accuracy (usually), the odds on two pavers being in direct contact is much less, and so spalling is less likely.

But, if you want to err on the side of caution, then you should fit the rubber mat before final consolidation.

 ruler
Forum Question Method for Block Paving - Harp - Jun 11th 2003
I would appreciate some general advice regarding a sort of DIY block paving project.

I have a large driveway which I wish to block pave, the area is about 50 ft x 50ft. I have had a number of estimates but am finding the costs that contractors wish to charge very high. In view of this, I am commencing getting the job done on a job by job basis.
Next week, I have a worker digging the drive and we will get a grab lorry to take the muck away.  

Q1. We are planning to dig down about 10 inches. Is this a sufficient level?
Q2. After this I propose to get a HGV to deliver around 40 tonnes of Type 1, spread this and then hire a wacking plate? Is this correct order and right amount of Type 1?
Q3. Do I think about my drainage when we come to lay the sand?

Many thanks in advance.
Harp

forum answer Suki
Jun 12th 2003
Well I would say 50 tonnes is a bit closer to the level. It depends how good the dig is. You really need to get it at least 10 inches from the final paving level (FPL) at which point you have certain fixed points that cannot be moved and dictate the fall of a drive. They are the dpc of the house and where the drive meets the pavement/road - these cannot be changed. You will need to think of drainage at this point and if you do not have a good fall away from the house you will need to think about placing gully drains or pot drains, but without seeing the job this is almost impossible to give advise on.

If you use a tight string line off these fixed points showing the FPL you can use a measure to check that you have 10 inches all over under the line. Then drop on the 53 tonnes of MOT class 1, then rake smooth and I would recheck then with the lines again to check you have around 110mm from string line to the top of the MOT after compaction (4-6 passes) and away you go. This is quite a big job to learn the ropes on, and could be an expensive mistake.

Out of interest, how much have you been quoted? We would do the whole job (230m²) to completion for around £9k

Harp
Jun 12th 2003
Thanks very much for the tips.

For info, quotes have ranged from £13k to £18k.

I really would not be looking to do it myself but am aiming to try and save some money by breaking the job into smaller stages by buying the materials myself and hiring some skilled labour on ad-hoc basis.

Will bear your estimate in mind, however. How much do you think it would cost just to lay the blocks?

Thanks once again
Harp

Suki
Jun 12th 2003
It's difficult to say - just to lay the blocks we certainly would not undertake such a job because we do not know what has gone into the sub-base/method etc and thus can not fully guarantee the job after we complete. You may struggle to find a company that will just lay but if you do find a firm, check their work out beforehand. We carry a full stage-by-stage porfolio with us, with about 40ish jobs in it with us on the piccys, and we tell our potential customers to visit and speak to anyone of them they choose. If you are proud of your work and have nothing to hide then show it off. smile

Where do u live??

Tony McCormack
Jun 14th 2003
Again, Suki's advice is sound. Bringing in different contractors to carry out different parts of the work leaves you with a very large potential headache if owt goes wrong. The block layers might blame it on the gang that placed and compacted the sub-base, while they might say it was the fault of the gang that did the excavation. By getting one contractor to accept repsonsibility for the whole job, you only have one point of contact in case of any problems.

I'm with Suki, too - we would never issue a guarantee with block paving unless we had installed the sub-base ourselves. I'm happy enough for someone else to have done the excavation, but, from that point onwards, I preferred all the construction work to be checked and approved by ourselves.

Splitting the job has got to be more costly than using a single contractor. You have two, three or more gangs, each looking to make a decent profit on what would be a relatively small job, instead of a single contractor making a fair profit on a reasonably sized job.

Regarding materials quantities and drainage issues, all of these are covered in excruciating detail on the main site - have aread through all of that before committing yourself to what could be a very long and very costly methodology.

Harp
Jun 16th 2003
Thanks once again for the advice.

I'm having the drive excavated on Friday, with a grab to take the load away.

Suki - I live in Luton. Without seeing the job, what would be your approx cost per sqm having completed the dig?

 ruler
Forum Question Block Laying Basics - Sirrocco - Jun 15th 2003
Hi all,

Just a couple of questions I need help with.

1) - I need 5 tonnes of DTp Type 1. I already have 1 tonne of white stones (they range in size from a 5p piece to just over 50p peice size) which used to border the old lawn, can I utilise these in the sub-base and add 4 tonne of DTp Type 1 to them?

2) - I am just using the drive (25 sq metres, slightly over 8 metres in length) to park 1 car on. Do I need 50mm or 60 mm blocks?

3) - Does the 50mm of grit sand need to be compacted (I think it does)?

4) - If so, when I lay the blocks, do I lay them directly onto the compacted grit sand or do I add a thin layer of loose grit sand on top of the 50mm compacted grit sand to bed the blocks on?

forum answer Tony McCormack
Jun 15th 2003
1 - scatter the old stone over the surface of the excavated sub-grade and then top up with genuine DTp1. Keep the old rubbish to a thin, base layer blinding over the whole area, rather than a 'block' of material in just one spot.

2 - 50mm will be fine, 60mm would be better, but it really doesn't matter for a residential driveway.

3 - 50mm is the maximum recommended thickness after compaction. Read the Screeding page for a fuller explanation.

4 - see above. I recommend the pre-compaction method, as it gives the best results in the longer term.

Good luck and let us know how you get on! smile

Sirrocco
Jun 19th 2003
Hi again,

I have finally dug out everything to 200mm and will soon be comencing laying the hardcore (dtp1) and compacting it.

Once I have done this I plan to lay the edging soldiers. I have been told it is a lot easier to lay the edging blocks on a dry mix and then lightly run a hose over them. Would you recommend this or is it best to mix the morter up?

Also I am concerned about weeds and other plant life growing underneath the blocked area. Again I have been told the black sheeting stuff that can be bought from B&Q specifically for stopping this is not very good and I should use heavy duty plastic sheeting. What would you advise for this? And at what stage should I lay this sheeting? Prior to laying dtp1 or prior to laying grit sand or prior to laying the blocks?

Also my driveway has a gentle slope to it running away from the house. Is it better to start laying the blocks from the bottom and working up(so that there are no cut blocks at the begining of the drive where the initial impact of the car will be felt) or is it best starting at the top and working downwards?

Tony McCormack
Jun 19th 2003
Sirrocco writted...
I have been told it is a lot easier to lay the edging blocks on a dry mix and then lightly run a hose over them. Would you recommend this or is it best to mix the morter up?

It's best to lay the edge courses on a semi-dry mix of concrete, as described on the main site. There's adequate moisture in the sands and gravels to initiate curing of the cement, so no need to add extra water by hose, by bucket or by any other means. You can use a wetter mix for the haunching, but a semi-dry mix is ideal for bedding.

Weeds - other than the really pernicious, nuclear-bomb proof weeds such as Japanese Knot Weed and Equisetum, the vast majority of weeds will not grow through a properly constructed block pavement. There's 200mm of heavily compacted, weed-unfriendly material between the sub-grade and the surface, and your average dandelion or daisy does not stand a chance of getting through that lot, whether there's a weed membrane there or not.

However, weeds will settle onto the surface of the completed pavement and grow into the joints, and no weed membrane can stop that, regardless of where it's positioned.

So, a weed membrane is not necessary beneath a properly constructed block pavement, and to use a sheet of polythene rather than a proper permeable membrane is a certain recipe for disaster. I don't know who's giving you all this duff information, but maybe you should start drinking in a different pub, because the expert you have there is a right numpty!

The use of membranes beneath block pavements is covered elsewhere on the website, but their purpose is to add stability to the construction, not to prevent weeds. Weed membranes are fine benath mulches and other loose surface dressings, but they are a complete and utter waste of time and money beneath a properly paved surface.

With any form of paving, you always start to lay at the bottom of a slope and work your way uphill. If you do it t'other road round, the paving starts to slips away from you as you lay it!  smile

Sirrocco
Jun 19th 2003
Thanks Tony,

I don't consider my drinking buds to be the experts, thats why I'm double checking with you smile

One more quick question for now.
My driveway will be encased with 2 lines of soldiers (one up each side), I know that I have to lay the outside line to give the blocks stability when laying but do I have to lay the inside set before as well? The reason I am asking this is - on your block patterns page - if those blocks are 200mm × 100mm then the area they cover is 1.4 square metres, is this usually exact? I want to minimise block cutting down the inside edge of the drive and my drive will be 3.0 metres wide exactly. Therefore if I lay both beds of soldiers I will have a gap of 2.6 metres to fill with block. Will the gap being an exact multiple of 200mm and 100mm? Is it unlikely I will have to cut any blocks down the inside edge? Or as I lay the blocks will aIfew mm extra get used up as I work my way across?

Sorry if these questions seem pretty basic to you but I don't want to balls the job up smile

p.s. I will be using the 90 herringbone pattern

Tony McCormack
Jun 19th 2003
It's never a good idea to attempt to predict the exact width of a block paved area prior to laying. In theory, you want a 3m wide driveway, and you have two edge courses, laid as soldiers, each 200mm wide, so, you'd think that 26 blocks, each 100mm wide, laid between the edge course would do the job perfectly, but it ain't that simple.

There's a 3mm joint between the blocks, so you need to allow for that. However, assuming that each joint will be exactly 3mm is fatal, as the figure of 3mm is an ideal, and, in real life, the joint will more than likely be somewhere in the range 2-5mm. So, if you laid 26 courses of block paving, you could end up with a width of between (26 × 102mm) 2.65m and (26 × 105mm) 2.73m, a range of 80mm.

If you want to be sure of using as few cut blocks as possible, then the only way to work is as follows....

1 - lay one edge course on concrete bed and then haunch the blocks so they are firmly held in place (unless they are up against a firm fixture, such as a wall). This is your fixed edge course.

2 - lay the opposite edge course on semi-dry concrete bedding, with ample spread of the bedding to the outside edge of the blocks. Lay these blocks at the minimum theoretical separation from the fixed edge course (2.65m, as calculated above). This is your free edge course.

3 - prepare your screed and lay the blocks as per normal instructions. This is the body of the paving.

4 - adjust the position of the free edge course blocks so that they give a tight joint against the full blocks of the body paving. The edge course blocks can move out on the generously wide bed you prepared for them in step 2 above. Just slide them over carefully, so that the level is not affected, just the alignment.
Once all of the edge course blocks have been moved as required you should check the alignment with a taut string line, as there will be some deviation, and, if you rely solely on creating a tight joint between the blocks of the body and those of the free edge course, it will look like a crippled dog's back leg. You will have to do a bit of 'give and take' with some joints being a touch wider than other so that the edge course looks straight.

5 - Once you're happy with the alignment of the free edge course, fix it in place with concrete haunching.

6 - cut in the half-blocks to complete the body paving, and then sand-up the joints. Leave the consolidation (wackering) until the following day when the freshly-placed haunching concrete will have set and will be better able to withstand the force of the vib plate.

7 - Pub!   smile

These Q's aren't basic - they're fundamental to the construction of a decent driveway, and the whole purpose of this forum is to answer these fundamental questions. smile

 ruler
Forum Question Tegula & Membranes - Dunedin - Jun 20th 2003
Is there a standard recognised Specification for laying Marshalls' Tegula Drivesett?

My contractor recommends concreting in the edging as opposed to the last row of blocks - any comments?

He also recommends a poythene sheet under the hardcore - is this necessary?

And finally his price is 70 pounds sq meter including material - does this sound reasonable (I am getting other quotes)?

forum answer Tony McCormack
Jun 20th 2003
Tegula Drivesett are laid in exactly the same way as any other concrete block paving. As long as the edges are properly restrained, it doesn't matter whether a kerb/edging is concreted-in or the edge courses themselves, as long as they are solid, do not move and can withstand the loads imposed on the paving.

However, this idea of using a polythene sheet is a Class A Indicator of Dodgy Contractor Syndrome. Polythene should never, ever, ever be used beneath block paving. It is the sort of gob-shite idea put forward by eejits who think they know how to lay block paving, but really shouldn't be allowed out of the house unsupervised, because they cannot tell the diff between a sheet of polythene and a geo-membrane, and don't understand the reasoning behind the inclusion of geo-membranes in certain constructions.

Here's something from an up-coming web-page on this very subject...

....So, a weed membrane is not necessary beneath a properly constructed pavement, and the suggestion put forward by some well-intentioned but misguided bodgers that a sheet of polythene or similar can be used in placed of a permeable membrane is a certain recipe for disaster. Polythene is impermeable, which is why it is used as a damp proof membrane in buildings, but to use it beneath an elemental pavement (block paving, flags/slabs, setts, etc.) will prevent the proper drainage of the pavement layers, which will, in turn, lead to saturation of the bedding layer. With unbound bedding materials (grit sand, etc), this can have the unfortunate effect of causing the paving layer to 'float' as the bedding material begins to act like a fluid. For this reason, impermeable membranes are not to be recommended beneath block paving, patios etc, unless some other form of sub-surface drainage is present.

However, the use of permeable membranes beneath elemental pavements is becoming more popular and is a perfectly valid construction. Their manifold uses and applications are covered elsewhere on the website, but their primary purpose is to add stability to the construction, not to prevent weeds.

The above quotation is now part of a completed page looking at the use of membranes beneath block pavements.

70 quid per square metre had better include all materials and VAT. I'd definitely get at least 2 more quotes if only because the notion to use a polythene sheet beneath the paving worries the pants off me.  sour

 ruler
Forum Question Mystery stains - Lewis - Jun 22nd 2003
Help ..I had a new paver walk way installed about 2 weeks ago. I now have white stains on a lot of the blocks in the center of them.

How do you get rid of them and what are they from

Thanks anyone in advance

forum answer Tony McCormack
Jun 23rd 2003
Sounds like efflorescence, which is not uncommon on new concrete pavers. Is it a dusty, white, mildew-like deposit on the surface of some, but not all, the blocks?

If you look at any manufacturer's catalogue, they all have a clause in the small print absolving them of any responsibility for effloresence, and, to be fair, there's not a great deal thay can do about it, as it's a natural phenomenon with most concrete products, and it occurs with clay pavers, vertical masonry, concrete castings etc.

It will disappear in time. Usually, a few weeks out in the summer rain will wash them clean, but there are some cases where the efflorescence has persisted for several months. There are products that claim to shift the deposits, which they do, but they are a temporary fix, and the eff. will be back again in a couple of weeks.

As your paving is new, give it at least 3 months to see if the apparent 'staining' gets any better, disappears altogether, or becomes really 'heavy'. In around 95% of cases, it will have disappeared completely by the time we get to September.   smile

 ruler
Forum Question Bedding layer drainage - SteveC - Jun 28th 2003
My problem relates to drainage at the front (bottom) of my soon-to-be block paved drive.

The original tarmac drive(s) had been down since the 1930's when the houses were built. I removed two layers of tarmac and checked sub base, etc. All OK, shouldn't get any more movement in the base.

I've bedded a soldier course all around the perimeter etc, and infilled with sand. However, we have just had a day's heavy rain, and I've realised that there is water collecting at the bottom of the drive "within" the soldier course, and all the sand within is waterlogged. The soldier course at the bottom is level with the pavement, which means that the bedding sand is lower, so I obviously need some type of drainage( or do I?).

I'm waiting for the sand to dry out before I start laying the blocks, but if I don't put any drainage in at the bottom of the drive, what will happen when it rains? Most of the rainwater will run off the surface anyway, but what about that which penetrates down into the sand layer etc?

forum answer Tony McCormack
Jun 30th 2003
You're worrying unnecessarily, Steve. Surface water may well be acccumulating at the lower end of your drive at the moment, but that's because there's plenty of room for it to do so. Once it's all paved-in, there's nowhere for the water to sit, and so it moves on, as it were.

Yes, some water will be retained for a short period by the sand bedding, but there is only so much water that can be held in voids between the sand grains, and once they are full, any further surface water will not be able to penetrate, so it will run off over the surface. Gradually, any retained water will seep away through the sub-base, leaving only that water which is held by capillary action, which is entirely natural for a sand.

What happens over the longer terms is that 'fines' are washed into the sand bedding and thanks to gravity, they end up at this low point, where they reduce the number and volume of the tiny voids (interstitial spaces, as they are sometimes called), so even less water can be retained by the bedding sand.

There are hundreds, probably thousands, of block-paved driveways in the same situations as you describe, and they manage to survive without any additional sub-surface drainage system, so I reckon your's will be fine, Steve.   smile

Good Luck!

SteveC
Jun 30th 2003
Thanks Tony
It's reasuring to know all's well.

Over the weekend it was warm and sunny, so the sand dried out a lot. So I've got all the blocks laid, and only the "cutting-in" bits are left to do now. Although today it's again pouring with rain, and I'm wondering now what sort of time do I need to leave the blocks before I can use a "whacker" plate on them?

Thanks again for your help. smile

Tony McCormack
Jan 11th 2003
As soon as poss! You mentioned previously that your edges are in and have set, so, as soon as you've finished cutting-in, and the weather is dry enough to sand-in the joints, you can get the vib plate going on the lot!   smile
 ruler
Forum Question Re-using a sub-base - Bulkington Mark - Jun 29th 2003
We had an extension built on our house last year which gave us a great opportunity to get rid of the broken slabs and blue bricks that had been masquarading as a drive for the last 12 years at least. Once these were removed we found the area in front of our house to be very soft as a result of an old soakaway. The soak away is no longer there and, after much excavation, the groundwork contractor capped off the soft area with 1.5 cubic metres of concrete and an amount of Type 1 spread on top. The rest of the drive area had approximately 5T of Type 1 spread on it but has never been compacted.

This sub-base has been down for around a year now and seems quite stable and we're faced with the decision of what to do now. We are considering a block paved drive formed with the Marshall's Tegula Setts or an imprinted concrete drive. In either case, should we remove all the sub-base, being somewhat unknown in quantity and depth, and start again, or perhaps leave the concrete cap and excavate the remaining drive as per normal for a new installation?

Any advice is greatly appreciated.

forum answer Tony McCormack
Jun 30th 2003
You say that the sub-base is quite stable - is there any sign of "pumping", which is the phenomenon whereby the soft sub-grade material is 'squished-up' through the sub-base by repeated trafficking? The tell-tale indicator is smud on the surface of the sub-base material.

If none is evident, I'd suggest that what you have is worth hanging on to, and the best way to proceed would be to level out what's there now, lay down a decent geo-membrane such as one of the Terrams (1000 is fine) or TDP115, top that off with regulating sub-base material as required to get to formation level, compact the lot and then lay the paving of your choice.

The choice of paving will have an effect on the preparation of the sub-base. If you opt for PIC, you're going to have to bring in a specialist contractor and they should examine the sub-base to determine whether it needs tittivating or replacing, so that they can issue their standard guarantee. However, if you opt for the Drivesett paving and plan to DIY, then the decision regarding the sub-base is yours.

Bulkington Mark
Jun 30th 2003
Thanks for the advice Tony. It's pretty much what our builder suggested. He employed the groundwork contractor before commencing the build. If we decide to go for the Drivesett we'll be employing a contractor to do the job. I guess they may want to excavate the sub-base again to comply with the Marshall's guarantee. Have you any recommendations for a contractor in the Warwickshire area? Those we've contacted so far (listed in the Marshall's approved register) have not been too inspiring.
Tony McCormack
Jun 30th 2003
Whereabouts in Warks? Email me.
Bulkington Mark
Aug 9th 2003
Hi Tony,

Thanks for your recommendations but I'm yet to decide who to engage as contractor for my drive. On a friends recommendation, I've just spoken with a local contractor who raised a couple of interesting points:
1) - All domestic paving blocks will be manufactured in 50mm thickness to conform to a new BS. Know anything about this?
2) - The concrete area I mentioned in my first posting will need to be removed and the ground excavated to get rid of the soft area, possibly with the addition of a membrane for stability, although I tend to agree with your comment that what we have is worth hanging on to. His reason for removing the concrete area is he will not be able to compact the blocks properly on top of it. Any thoughts?

Cheers
Mark Patrick
Warwickshire

Tony McCormack
Aug 11th 2003
A colleague who works for one of the largest manufacturers in the UK told me some time ago that there were mutterings about bringing 50mm 'driveway' blocks within the scope of BS6717, but whether they ever will, I can't say. My understanding was that there were 'issues' with the tensile strength of 50mm blocks and making them strong enough to meet the test requirements would eliminate any cost saving made by reducing block thickness from 60mm to 50mm.

I can't see them introducing a wholly new BS purely for driveway blocks, so BS6717 would need to be amended, I suppose, but then, we are supposed to be moving towards a pan-European standard, and 50mm blocks are uncommon on the continent. To be honest, I don't think bringing 50mm blocks within the scope of a British or European Standard is all that important, but I'll ask around and see if anyone else is aware of this.

Turning to the issue of re-using the concrete base, laying block pavers over a concrete base is an accepted and approved methodology. If your contractor has a problem compacting blocks laid over a concrete base, it suggests their skills and experience are more limited than should be expected.

 ruler
Forum Question Block paving on sand/cement bed - A Novice - Jun 30th 2003
I decided to ask a family friend who is very good at DIY to help me build a block paving driveway and path. I am a complete novice at most DIY projects, but I did take the time to do some research.

My understanding is that a driveway should be made up in 3 basic layers. MOT Type I (approx 100mm), sharp sand which is split into 2 layers, approx 35mm compacted, and a 15mm screeded layer, and the final layer is the block paving. I explained this to our friend, but he has gone on to make the driveway using the following layers. Bottom layer is MOT type I (100mm). Middle layer is a mix of sharp sand (5parts) to cement (1part) plus a bit of water, ie semi dry this is the evening-out layer so ranges in thickness from say 50mm up to 100mm. Final layer, block paving.

His reason for using cement is that he cannot see how sand will stop the paving from sinking. My view is that if the edges are firmly bound in and the MOT layer is firm, the block paving has nowhere to go. I'm worried that the cement which creates a semi hard layer, will start to crack under weight or due to changing weather conditions (I live in London). Am I justified in being concerned, or has what our friend done likely to work?

Many thanks

forum answer Tony McCormack
Jun 30th 2003
What your mate has done is a classic illustration of the adage that "A little knowledge can be a dangerous thing".

We do not use a cement-bound bedding layer beneath flexible block paving. The clue is in the title.... FLEXIBLE block paving. His method is a sort of halfway between flexible and rigid but doesn't meet the spec for either, to be honest.

Just how this botch will perform over the longer term I can't say, but I wouldn't be too optimistic. It probably will crack, but how that will affect the appearance of the blocks, I can't predict without seeing the job itself. I'm guessing you'll experience a degree of channelisation (rutting) and you may well find that some areas of the paving start to experience a greater degree of efflorescence.

I'm not sure that it's worth ripping it up and starting again, but I certainly wouldn't be buying a pint for that particular mate the next time I see him!

A Novice
Jun 30th 2003
Not what I wanted to hear, but many thanks for the reply.
 ruler
Forum Question Working from the middle to the edge? - DavidGKR - Jul 2nd 2003
Dear All

I have seen block paving laid in two ways. The first, which I believe to be the norm, is to lay the edge blocks first and then in fill with the pavers and do the cuts. The other I have seen is where the pavers are laid first and then the edge laid afterwards on concrete and the whole area whacked at the same time including the edge. I was told that this method would reduce the amount of cuts and ensure that the pavers meet the edging blocks perfectly level.

Is this second approach ok to adopt?

forum answer Dwayne
Jul 2nd 2003
We had someone out to block pave our back path. He claimed to be a specialist so we let him get on with it. EXPENSIVE mistake, after he finished he passed the wacker plate over the whole path, sure it was quicker and because the cement had not gone off properly the whole path spread out leaving wide joints.

I have since found this site and have decided that I can do a better job myself. Especially as when I tackled the company who did the work about it, they argued a lot, then called us names then hung up. sulk

I have read on this site that the edging must be done first.

Suki
Jul 2nd 2003
We always set edgers in first, be it a bullnose edger, block paviour or or curbstone, This is because we need to surround the sub-base layers and keep them contained within the perimeter of the paved area. Where the paving is against the house or wall it will be restrained by the solid walling/footings. As to using a vib plate over blocks that are on unset mortar - one word MUPPETS!
Tony McCormack
Jul 6th 2003
The method that relies on making the edge courses fit the paving, rather than the paving fit the edge courses, is popular with the gangs that like to think they are 'professional' but are actually deluding themselves and their clients.

The problem with that method is that the edge blocks end up being laid on a bed of sand with just a trowelful of mortar or concrete slapped behind them. This is NOT strong enough to restrain the paving in the longer term. Yes, it will last until the cheque has cleared, but it's an unacceptable construction to any real professional contractor.

However, the method of laying the edge courses last is acceptable as long as the edge blocks/kerbs or whatever is being used, are bedded on and haunched with concrete, giving a properly constructed, secure restraining edge course.

edge haunching

As long as the finished job has the sort of construction shown on the right hand side, it doesn't matter in which order the blocks are laid, but, the problem with the "edges last" approach, is that the construction shown on the left is the usual outcome. sulk\

DavidGKR
Jul 7th 2003
Thank you for all your replies and comments, luckily my driveway did have the combined bed and haunch edge blocks..!
 ruler
Forum Question More about edge courses - Peter H - Jul 3rd 2003
I had planned to attempt to block pave approx 14 sq mts for a patio/parking area at the end of my garden after finding your great site. I've dug out and layed the dolomite and was ready to start the edging when my back started complaining.

I've found someone (recommended) who will lay the blocks for £60. He says it will be done in one day (is it possible for the concrete to be set properly?) and that there's no need to lay edge blocks on concrete, haunching will suffice. I know this is not the way shown on your site but I would appreciate yours or any other opinions as he's doing the job this saturday.

Thanks

forum answer Tony McCormack
Jul 6th 2003
It's very possible to lay 14 m² in a single day, and do it so that the blocks can be consolidated without upsetting the haunching, but I'd want to know more about the planned methodology before agreeing to let him undertake the job.

Have a look at the thread above about working from the middle or the edge - this includes an image I've posted showing why haunching alone is NOT sufficient to restrain a block pavement. If your man thinks haunching alone IS sufficient, then he's a cowboy, and you can tell him I said so!

Peter H
Jul 6th 2003
Too late he's galloped off on his horse. Besides, I think he would of knocked all my teeth out if I had passed your message on.

The finished job looks good but I have not driven on it yet. He assured me it would not move as the edge blocks( layed longways) butt up against the excavated area on 3 sides and paving slabs on the other.

I suppose I could relay the edge bocks on concrete if it looks like it may move, or is there an alternative that could be used in situ along the lines of the prefabricated edging?

Tony McCormack
Jul 7th 2003
There's a whole page outlining the various alternatives to concrete bedded edge blocks - click here to access it.
ruler

Previous Page | Main Index | Block Paving Index | Next Page arrow

spacer milonic
Brew Cabin Archive
navigation dhtml
courtesy of Milonic
spacer