Posted: Thu Mar 17, 2011 8:53 pm
I have laid a 200mm sub base using 803 compliant type 1, I have taken the advice from this site and laid it in two 100mm layers. I have used a very heavy petrol wacker plate (A Benford, I think) and done at least 17 passes.
I have today had a delivery of around 18 Tonnes (cement, Ballast etc) and I noticed that the lorry left indentation of around 5 or 6mm (at worst).
My question is; should this concern me or not? as I plan to lay recycled gritstone setts. Do I need to hire a road roller type machine? will it make a big difference? is an 18 tonne lorry always going to make a mark in bare type 1.
Sorry for so many questions but if the base is not right there is little point in continuing until I get it right
I have today had a delivery of around 18 Tonnes (cement, Ballast etc) and I noticed that the lorry left indentation of around 5 or 6mm (at worst).
My question is; should this concern me or not? as I plan to lay recycled gritstone setts. Do I need to hire a road roller type machine? will it make a big difference? is an 18 tonne lorry always going to make a mark in bare type 1.
Sorry for so many questions but if the base is not right there is little point in continuing until I get it right