Got a bit of a job on at the moment, 1200m2 farm shop parking area that was hastily (and badly specc'd and laid some 10 years ago!)
Been quite a bit more work than we anticipated - but with the financial agreement with the customer, I hasten to say!
We've dug out circa 400t of material (Tuesday) and stoned up/surfaced back with base course today (ready for surface course) one side of the car park - and have to get the other side ready for surfacing for Monday AM, dig out and stone up the customer entrance area (There is an alternative customer entrance round the side) - plus installation of the last 20M of power cable/alarm cable ducting across a busy entrance splay - on a busy Saturday!
On-site for 6am, it's going to be another 10-12hr day Plenty of planing, digging, bucket brushing and irate farm shop customers again! Wish me luck........
Edited By Dave_L on 1174077154
Been quite a bit more work than we anticipated - but with the financial agreement with the customer, I hasten to say!
We've dug out circa 400t of material (Tuesday) and stoned up/surfaced back with base course today (ready for surface course) one side of the car park - and have to get the other side ready for surfacing for Monday AM, dig out and stone up the customer entrance area (There is an alternative customer entrance round the side) - plus installation of the last 20M of power cable/alarm cable ducting across a busy entrance splay - on a busy Saturday!
On-site for 6am, it's going to be another 10-12hr day Plenty of planing, digging, bucket brushing and irate farm shop customers again! Wish me luck........
Edited By Dave_L on 1174077154