How do you go about putting steps in a hill - Natural stone steps up a hill

Other groundworks tasks, such as roads and footpaths, terracing, fencing, foundations, walls and brickwork, tools and plant.
Post Reply
Forestboy1978
Posts: 1000
Joined: Sun Oct 23, 2011 9:57 am
Location: southampton, hampshire

Post: # 97017Post Forestboy1978

Roots aren't a problem as I think the shrubs have grown out maximally. Might need to remove some but new growth shouldn't be an issue.

There some steps there already but only 2 or 3 out of the 13 are still intact/ safe to walk on. They are natural stone, not mortared so I would want to at least use the stone and get more of the same. Perhaps clean it up a bit with the pressure washer.

It's not really my thing but it's a regular customer and she's going away for 2 months so no pressure to get it done. I'm a bit bored so might give it a go if it's not too hard.

Any advice on sub base etc would be grand.

Cheers

Forestboy1978
Posts: 1000
Joined: Sun Oct 23, 2011 9:57 am
Location: southampton, hampshire

Post: # 97018Post Forestboy1978

Image

Forestboy1978
Posts: 1000
Joined: Sun Oct 23, 2011 9:57 am
Location: southampton, hampshire

Post: # 97019Post Forestboy1978

Image

Forestboy1978
Posts: 1000
Joined: Sun Oct 23, 2011 9:57 am
Location: southampton, hampshire

Post: # 97033Post Forestboy1978

OK I've figured it out. I'm gonna take everything away and carve steps into the actual hill out of the dirt. Then tamp down and lay a membrane.

Then string line off where each step will be positioned.

Then I will compact in some limestone scalpings to about 2-3" before placing all my risers of which there will be 12/13 at 8" high. Not sure if 2-3" is enough but it's clay hard soil. I'll mortar the stones with a 4-1 mortar, leave to dry over night and then back fill with more scalping behind the risers and compact and then fit the goers.

That sound alright? Roughly what time scale should I bill her for do you think? I understand it will take me longer and that's alright. I don't mind as long as I learn something.

Cheers

r896neo
Posts: 521
Joined: Wed Feb 22, 2012 9:38 pm

Post: # 97039Post r896neo

I have built a few long winding sets of steps in sloping gardens, one of which you can see on my website if you like.

In that one each riser has a concrete footing and then the bullnose flag laid on top. On the wider treads hardcore and gravel form the rest of it.

Steps like this take ages and usually gardens that need steps are steep and often have terrible access so guesstimate the time you think you'll need and add at least another half.

lutonlagerlout
Site Admin
Posts: 15184
Joined: Fri Aug 04, 2006 12:20 am
Location: bedfordshire

Post: # 97044Post lutonlagerlout

sounds like a fail forestboy

the couple of steep steps we have done we excavated the topsoil and then shuttered the steps

poured concrete (with difficulty ) with mesh

and then laid the risers and treads on the concrete

as said it was a pita job

LLL
"what,you want paying today??"

YOUR TEXT GOES HERE

lemoncurd1702
Posts: 712
Joined: Sat Oct 19, 2013 7:56 am
Location: South Wales
Contact:

Post: # 97049Post lemoncurd1702

Have you considered sleeper risers or pegged in boards backfilled with gravel. Could be a more economical option.

If its gotta be stone risers and treads then concrete all the way, When I've done similar in the past I use rapid cement so it's a quick build.

Some of the treads may need to be deeper/longer than others as it looks as though the slope is of varying degrees.

To be honest I would not try to over engineer something like this, build each step separate rather than as a mass. The present steps are a mish mash and whatever you do will be an improvement.
On your own 2 days if your under 30 years old. Over 30 but under 40 1.5 days cos u know what your doing. Over 40, 3 days cos u can't be arsed anymore.
Cheers
Lemoncurd

Tony McC
Site Admin
Posts: 8346
Joined: Mon Jul 05, 2004 7:27 pm
Location: Warrington, People's Republic of South Lancashire
Contact:

Post: # 97068Post Tony McC

The thing with steps is that they want to slide down the slope, so it's essential that they are well and truly anchored in place.

This might be achieved with deep stones set well into the sub-layers, or it might be achieved by relying on concrete. If you;re not sure about the ground conditions or, as it seems, you've not much experience in building steps, then concrete as a bed/foundation is your best option
Site Agent - Pavingexpert

Forestboy1978
Posts: 1000
Joined: Sun Oct 23, 2011 9:57 am
Location: southampton, hampshire

Post: # 97076Post Forestboy1978

Cheers for the advice guys. I've declined the job cos she wants it done cheap for 1 and 2 I've got enough work. Sounds like it will be a pain to do right.

Ps sleepers aren't an option due to slippyness!

Pps yeah I checked your site mate. Looks nice. These ones would be more of a pain than those though cos they would be back to back with less area to play with for anchoring etc.

As usual guys, invaluable :-)