Someone has asked me to quote to lay 70m2 Raj Blend in a random pattern.

How long would you say to lay for two guys (one mixing and one laying)

Any ideas would be helpful.

Simon
Maintenance Man

dig dug dan
Posts: 2504
Joined: Thu Jul 10, 2003 10:20 pm
Location: hemel hempstead,herts. 01442 212315

Post: # 92218Post dig dug dan

Simple square, no cuts or drains etc, two days for experienced guys not including pointing. Three days if lots of fiddly bits
Dan the Crusher Man
01442 212315
www.crusherhire.co.uk
"a satisfied customer? we should have them stuffed!"

bodgeitandscarper
Posts: 345
Joined: Tue Aug 07, 2007 9:23 pm
Location: Hereford

Post: # 92222Post bodgeitandscarper

is this including pointing using the old school method?

Thanks for replying
Maintenance Man

dig dug dan
Posts: 2504
Joined: Thu Jul 10, 2003 10:20 pm
Location: hemel hempstead,herts. 01442 212315

Post: # 92224Post dig dug dan

Not including pointing of any description
Dan the Crusher Man
01442 212315
www.crusherhire.co.uk
"a satisfied customer? we should have them stuffed!"

lutonlagerlout
Site Admin
Posts: 15184
Joined: Fri Aug 04, 2006 12:20 am
Location: bedfordshire

Post: # 92225Post lutonlagerlout

2 days dan?
i have loads of work for you :;):
i reckon to lay average 15-18 m2 per day
we have had good days of 40m2 but then you get a shite day of 10m2 due to cuts or whatever
thats 3 of us
for 70 m2 just laying i would say 4 days 3 men
and 1 good day to point
overall total cost around £7-8k labour and material
LLL :)
"what,you want paying today??"

YOUR TEXT GOES HERE

r896neo
Posts: 521
Joined: Wed Feb 22, 2012 9:38 pm

Post: # 92231Post r896neo

With flags all stacked close by and ready mixed mortar I have laid 20m in a day on my own so i would be between the 2 but closer to luton.

A 2 man team mixing on site should be able to lay 25m per day

pointing that with mortar would also take the guts of a day for 2 men

Carberry
Posts: 1366
Joined: Fri Apr 15, 2011 9:05 pm
Location: Edinburgh

Post: # 92233Post Carberry

lutonlagerlout wrote:2 days dan?
i have loads of work for you :;):
i reckon to lay average 15-18 m2 per day
we have had good days of 40m2 but then you get a shite day of 10m2 due to cuts or whatever
thats 3 of us
for 70 m2 just laying i would say 4 days 3 men
and 1 good day to point
overall total cost around £7-8k labour and material
LLL :)
This.

And it's a random pattern which is always a pain in the ass.

dig dug dan
Posts: 2504
Joined: Thu Jul 10, 2003 10:20 pm
Location: hemel hempstead,herts. 01442 212315

Post: # 92234Post dig dug dan

no wonder i have so much work!
Dan the Crusher Man
01442 212315
www.crusherhire.co.uk
"a satisfied customer? we should have them stuffed!"

lutonlagerlout
Site Admin
Posts: 15184
Joined: Fri Aug 04, 2006 12:20 am
Location: bedfordshire

Post: # 92237Post lutonlagerlout

I will make us millionaires Dan :;):
we all know the craic, good days and bad days

I wouldnt want to price a job on the assumption that we could lay 35M2 a day

pure labour I charge £20 per metre lay and cut and this nearly always achieves what we want to earn

obviously access is one of the biggest issues

cheers LLL
"what,you want paying today??"

YOUR TEXT GOES HERE

mickavalon
Posts: 661
Joined: Mon Feb 21, 2005 11:54 am
Location: Birmingham, west midlands, UK
Contact:

Post: # 92239Post mickavalon

I once spoke to a director of a pretty large scale landscape company, about 30+ guys, and they expect their skilled blokes to lay 10m2 per day, that's with a labourer. I reckon myself and the guys to do about the same as LLL, we also have good days and awkward pain in the arse days.
Gi it sum ommer