Ready mix mortar, how many bricks?

Other groundworks tasks, such as roads and footpaths, terracing, fencing, foundations, walls and brickwork, tools and plant.
Post Reply
tomo8
Posts: 32
Joined: Fri Mar 05, 2010 1:29 pm
Location: merseyside

Post: # 84401Post tomo8

Were starting a house this week an its pre mixed mortar with a dye in. Weve got to order as we go an dont want to waste any.

Its ages since we used pre mix an cant remember how many bricks you can lay for 1m3??

Got a feeling its 1000-1200.

Anyone any ideas?

Cheers

lutonlagerlout
Site Admin
Posts: 15184
Joined: Fri Aug 04, 2006 12:20 am
Location: bedfordshire

Post: # 84403Post lutonlagerlout

depending on frog size,frog up, frog down,10mm beds etc
around 12-1400 bricks to a metre2 of compo

it used to be 1000 bricks to a yard2 of sand but a yard2 is a lot less than a metre2

cheers LLL
"what,you want paying today??"

YOUR TEXT GOES HERE

Brucieboy
Posts: 162
Joined: Sun Jul 17, 2011 1:21 am
Location: Essex

Post: # 84404Post Brucieboy

Tomo - if you're using retarded ready-to-use mortar, 1 m3 will lay about 2000 solids (range 1700 -2400) and about 1600 perforated or frogged (range 1300 to 1800) assuming no wastage.
Retired DIY'er

tomo8
Posts: 32
Joined: Fri Mar 05, 2010 1:29 pm
Location: merseyside

Post: # 84408Post tomo8

Cheers for that felas.

henpecked
Posts: 1328
Joined: Thu Mar 26, 2009 9:00 am
Location: Warwickshire
Contact:

Post: # 84415Post henpecked

Its about a pack a tub of gobbo (1/3 cube)

lutonlagerlout
Site Admin
Posts: 15184
Joined: Fri Aug 04, 2006 12:20 am
Location: bedfordshire

Post: # 84417Post lutonlagerlout

in the real world bruce that is unlikely
i never liked those tubs,
day 1 like soup
day 2 ok-ish
day 3 like floor screed
if you got caught wetting it up or adding fairy it was down the road
we used tonne bags of ready dyed sand last year tommo that worked out good because if it rained you didnt have to worry
a metre a day would be good going for a 2 and 1 gang
LLL
"what,you want paying today??"

YOUR TEXT GOES HERE

digerjones
Posts: 889
Joined: Fri Jan 18, 2008 9:32 pm
Location: cheshire

Post: # 84420Post digerjones

the local buildbase [b,m] has got a silo and i have only seen i tub go out all the times i have been in there. and the silo must have been there 3 years now. it just dose'nt seem very popular, i would use it on the right job.
dylan

Brucieboy
Posts: 162
Joined: Sun Jul 17, 2011 1:21 am
Location: Essex

Post: # 84424Post Brucieboy

LLL - you're quite right. Retarded ready-to-use mortar is very difficult to produce consistently due to the many variables involved - the weather being one. Furthermore, it's very subjective. What's good muck to one brickie is absolute sh*t to another. A lot also depends what brick is being laid. For heavy, non-absorbant solids such as Class A, the brickie wants it fairly stiff, for highly absorbant bricks, it needs to be more workable. Getting a good compromise when doing a milk run with the same base mix is an art (mastered only by a few). The main reason the target number of bricks per m3 isn't achieved is down to wastage - difficult to quantify as it depends on the quality of the mortar, the weather (particularly when on day 2 rain or freezing conditions stop play) and site practice.

It's why the dry silo system is becoming more and more popular, particularly for the larger site. The mortar consistency can be changed quickly and the sytem shut down when you don't need it.
Retired DIY'er

henpecked
Posts: 1328
Joined: Thu Mar 26, 2009 9:00 am
Location: Warwickshire
Contact:

Post: # 84431Post henpecked

Rain = tarp. Frost = cellotex on tub. Easy

If it gets fruzzed, it will be piss-like. If your there when the guy drops. he will wet it up as its poured if its too stiff. Be careful with dyed mortars ,as wetting will change the shade .... sightly

tomo8
Posts: 32
Joined: Fri Mar 05, 2010 1:29 pm
Location: merseyside

Post: # 84440Post tomo8

Id rather not use it, but the client wants it and has arranged for it. He wants a normal pre mix for the blockwork, which i dont want!!

Going to tell him to get sand an cement for block.

Brucieboy
Posts: 162
Joined: Sun Jul 17, 2011 1:21 am
Location: Essex

Post: # 84443Post Brucieboy

If you're forced to use it, as henpecked says, ensure you're on site when it's delivered. That way you've got a better chance of getting what you want. Depending on how much has been ordered relative to the size of the mixer, these guys often do milk runs with very early starts generally on site well before 7.00 am for their first drop. If batched correctly, it should remain useable for two working days.
Retired DIY'er