Posted: Fri Jun 11, 2010 8:31 am
by loudog
Hi i have been on the black stuff for 25 years now and in that time i have done a few concrete jobs.
My question is I have a 60sqm slab to concrete (drive) I am getting it conveyerd in and wanted to know how long i have to work this concrete
Kind regards
Loudog

Posted: Fri Jun 11, 2010 9:12 am
by cookiewales
loudog wrote:Hi i have been on the black stuff for 25 years now and in that time i have done a few concrete jobs.
My question is I have a 60sqm slab to concrete (drive) I am getting it conveyed in and wanted to know how long i have to work this concrete
Kind regards
Lou Dog
in these temperatures you dont get long dont just dump it all in start from one end level as you go dont let them them rush you you will need at least 2 other helpers who know what there doing :;):

Posted: Fri Jun 11, 2010 11:34 am
by loudog
hi yeah thanks for the quick reply mate, there is 3 of us all together, shuttering all in, would i have a couple of hours do you think

Posted: Fri Jun 11, 2010 1:00 pm
by cookiewales
loudog wrote:hi yeah thanks for the quick reply mate, there is 3 of us all together, shuttering all in, would i have a couple of hours do you think
yep but well prepared and ready is the key when it goes its gone even trying to add water later is a fail good luck :;):

Posted: Fri Jun 11, 2010 5:37 pm
by lutonlagerlout
well if its 60 m at 100 mm thick thats 6 M3 the barrowmix crowd we use allow 40 minutes per metre barrowed but normally its more like 20 minutes per metre when access is close.
as cookie rights says dont let them rush you in to taking it in 1 big heap
2 lads barrowing and 1 levelling (we did 2 metres this afternoon but it was a 100M walk to the shed base)and we did it in an hour
most important thing is the slump,
too wet and you will be there till dark
too dry and it wont trowel up for love nor money
all the best
LLL :)

Posted: Sat Jun 12, 2010 11:14 am
by loudog
thanks for all your comments, i am having a conveyer belt so wont be barrowing it which will give me a bit extra time

Posted: Sat Jun 12, 2010 11:39 am
by lutonlagerlout
the barrow mix people we use has a kind of conveyor
seen here the main thing is have it at your own pace.
i hate shovelling crete as its curing

the readymix drivers all fell out of the ignorant tree and hit every branch on the way down :;):
good luck lou
LLL

Posted: Sat Jun 12, 2010 11:52 am
by cookiewales
lutonlagerlout wrote:the barrow mix people we use has a kind of conveyor
seen here the main thing is have it at your own pace.
i hate shovelling crete as its curing

the readymix drivers all fell out of the ignorant tree and hit every branch on the way down :;):
good luck lou
LLL
very well said luton when they start there spiel only got 30 mins need to dump it . i normaly say dont bother take it back that cures them :;): :;):