Page 1 of 2
Posted: Sun May 29, 2011 9:35 pm
by fairview groundworks
Hi
I need some of you big boys to get your thinking caps on. I've done some work for local widelife office scraping little strips of open heath land with my 1.5t machine.
They have asked me how much it would cost to scrape 1 hectare. They need to apply for grants so a day rate doesn't work.
need to take off about 4 to 5" load dumper and remove 300m to tip, thought of using 2 dumpers and a 6 or 8t machine
but
how long might it take to do a hectare or how much has anyone else shifted in a similar way ( eg turf or topsoil) . Someone on here moved a rugby training pitch I remember!
Thanks in advance
D
Posted: Sun May 29, 2011 10:24 pm
by Pablo
a hectare is just under 2.5 acres I've stripped 2 acres before in similar circumstances and it took 7-8 days if I remember right. I used a 7.5 komatsu a 2 6 tonners and realised pretty quickly that i should have got a bigger digger. They look big on a small site and tiny on a big site. If i was you i would allow 10 days labour and hire and at least 70litres of diesel a day.
Posted: Mon May 30, 2011 12:00 am
by local patios and driveway
14t excavator and a 9t dumper will do a hectare in 2 days with ease. are you an experienced groundworker or just starting out?
Posted: Mon May 30, 2011 8:23 am
by lutonlagerlout
I am sure giles will have the definitive answer on this but as has been said bigger is better
i would have a 17t hymac and 2 6 tonne dumpers,plus might be cheaper to hire a muck lorry to take it away if it has to go
LLL
Posted: Mon May 30, 2011 11:12 am
by Pablo
They've not made Hymac's for 30 years Tony you're showing your age mate.:laugh:
Posted: Mon May 30, 2011 11:55 am
by GB_Groundworks
Posted: Mon May 30, 2011 5:56 pm
by lutonlagerlout
Pablo wrote:They've not made Hymac's for 30 years Tony you're showing your age mate.:laugh:
Busted! :laugh:
LLL
Posted: Mon May 30, 2011 8:04 pm
by fairview groundworks
superb responses. I have been an owner driver of a 1.5 jcb for 7-8 years and done lots of tracks, trenches, augering etc etc. I hire in when bigger stuff needed but when asked for a price for a hectare, getting it wrong could be a right pain.
Its only got to be moved 500-700 m. Ground is OK and doesn't matter how it ends up.This is a summer job although we might have just had summer!
Ground is part mulch part bracken and part heather.
Thanks for the ideas on time v area etc, gives me more to get a figure
D
Posted: Mon May 30, 2011 8:23 pm
by GB_Groundworks
I'd be thinking 4-5k ish but some guys work on £2/m3 moved but there moving more than 1500m3 so £3 to £4 a m3 should see you right depending on your hire/movement costs.
Posted: Sun Aug 14, 2011 4:59 pm
by bobbi o
Trying to post a pic in a size that you can see whats happening but have given up. anyway...
need to level an area of a field,approx 100 mtrs long x 40 mtrs wide,varying in height by 3 metres from lowest(and finished level) to highest point along its length. any arisings can be lost in low spot adjacent to this new level area.
quetion i have is what machinery would be required and in what timescale?
Posted: Sun Aug 14, 2011 10:51 pm
by haggistini
Just done the math at £4 per M3 ...... I'm knocking the paving on the head and buying a machine!
Posted: Sun Aug 14, 2011 10:57 pm
by haggistini
No I'm not!!! I'd have to sub it out tho!
Posted: Mon Aug 15, 2011 7:57 pm
by GB_Groundworks
bobbi o wrote:Trying to post a pic in a size that you can see whats happening but have given up. anyway...
need to level an area of a field,approx 100 mtrs long x 40 mtrs wide,varying in height by 3 metres from lowest(and finished level) to highest point along its length. any arisings can be lost in low spot adjacent to this new level area.
quetion i have is what machinery would be required and in what timescale?
easiest is 13 ton class machine and 6 ton+ dumper get the biggest you can,
but bigger = quicker but equals higher fuel costs, less machine to hire, higher transport costs, most plan hire firms nervous about hiring bigger machines out to non groundworkers etc.
ideal setup would be 13 toner and a d6 size dozer, as you'll need to save the top soil and pile up off the job then loose the sub soil across to form your level on the -/+ 3m cut so you'll be cutting 1.5 in some areas and filling in others.
id do it with my js130hd(16 tons) and either 9 ton site dumper or tractor and 12 ton dump trailer depending on site conditions etc.
should take 2 experienced guys 3 weeks max assuming good weather and good machines.
i did a 60x40m 3m cut and fill with a 7 ton machine, 6 ton dumper on my own and fine levelled the top soil in 6 days. but was hard going.
Posted: Mon Aug 15, 2011 10:47 pm
by Pablo
GB_Groundworks wrote:need to save the top soil and pile up off the job then loose the sub soil across to form your level on the -/+ 3m cut so you'll be cutting 1.5 in some areas and filling in others.
It's not a cut and fill Giles he's taking his level from the lowest point and working into 3m at it's highest and the spoil is being filled into somewhere adjacent to it. Would that make a difference.
Posted: Mon Aug 15, 2011 11:11 pm
by bobbi o
GB-what about a 20+ tonne dozer?
will try and get a pic up.