Posted: Tue Sep 29, 2009 5:54 am
I have bveen asked to do the groundwork for a childrens playground, I would be grateful for some help on the following if anyone has any experience
Dig out area for cable runway approx 33.5m x 4m to depth of 0.25m, supply battens and membrane and fill with loosefill once equipment installed.
Is this an ordinary geo-textile membrane or something special for loosefill, also I presume the battens would be ordinary roof batten jus to hold down the membrane. If it is a geotextile membrane how do I stop the edges fraying if there is no edging between it and the surrounding ground
Construct mound approx 7 m wide by 12 m long with compacted height of 2.5 metres using recycled materials and topsoil recovered from other excavations. Re-seed area once installation complete.
What is the minimum depth for topsoil?? Also, I presume I would have to build up the mound in layers and compact....what thickness would the layers be if I use a wacker
Thanks in advance for any help
Jim Morrison
Dig out area for cable runway approx 33.5m x 4m to depth of 0.25m, supply battens and membrane and fill with loosefill once equipment installed.
Is this an ordinary geo-textile membrane or something special for loosefill, also I presume the battens would be ordinary roof batten jus to hold down the membrane. If it is a geotextile membrane how do I stop the edges fraying if there is no edging between it and the surrounding ground
Construct mound approx 7 m wide by 12 m long with compacted height of 2.5 metres using recycled materials and topsoil recovered from other excavations. Re-seed area once installation complete.
What is the minimum depth for topsoil?? Also, I presume I would have to build up the mound in layers and compact....what thickness would the layers be if I use a wacker
Thanks in advance for any help
Jim Morrison