Posted: Fri Jan 28, 2005 5:15 pm
Say you construct a car park with standard:
25mm Wearing Course, 50 Base Course, 200 Type1, Geotextile.
The top WC and BC are impermeable, yet everything below is permeable.
So why can't you stop short of your edge with the WC and BC? The run off would drain to the edge through the Type 1 past the geotextile and infiltrate below.
Saturation of the subgade / subbase and loss of strength supporting the WC / BC ?
25mm Wearing Course, 50 Base Course, 200 Type1, Geotextile.
The top WC and BC are impermeable, yet everything below is permeable.
So why can't you stop short of your edge with the WC and BC? The run off would drain to the edge through the Type 1 past the geotextile and infiltrate below.
Saturation of the subgade / subbase and loss of strength supporting the WC / BC ?