Posted: Mon Oct 16, 2006 5:36 pm
I have a two stage private drainage system.
The last brick chamber, which attaches to the weeper drains has moved.
This means that water lays in the chamber and the two outlets from the chamber are higher than the drainage pipes.
Can anyone suggest a solution.
I have thought of removing the brick inspection chamber and replacing with a plastic unit.
I also thought about some sort of U bend arrangement where the pipes leave the chamber, but this would still leave water lying in the chamber (As will still will not drain), and would not allow rodding in future.
The last brick chamber, which attaches to the weeper drains has moved.
This means that water lays in the chamber and the two outlets from the chamber are higher than the drainage pipes.
Can anyone suggest a solution.
I have thought of removing the brick inspection chamber and replacing with a plastic unit.
I also thought about some sort of U bend arrangement where the pipes leave the chamber, but this would still leave water lying in the chamber (As will still will not drain), and would not allow rodding in future.