Posted: Sat Feb 19, 2011 12:23 pm
by rolysatch
hi

Great site!

Reading the guide it says "75mm compacted thickness of DTp1 or of 50mm crusher run" so when i order the dtp1 and i need a compacted depth of 75mm what thickness would i be looking at uncompacted approx? should i base my calcs for ordering corrct quantities on 100mm would that be enough to compact down to 75mm?

any advice appreciated

Roly

Posted: Sat Feb 19, 2011 1:16 pm
by ilovesettsonmondays
hi .a tonne to ten sqm2 wont be far out.

Posted: Sat Feb 19, 2011 6:44 pm
by rolysatch
that's great thanks :)

Posted: Sat Feb 19, 2011 9:34 pm
by Big Phil
1 ton of limestone subbase will give you 2.2m3 compacted. you'd have to do the maths to calculate your volume based on m2 area and mm depth.

Posted: Sun Feb 20, 2011 7:39 am
by Mikey_C
there is calculator on the website here. don't forget the dumpy/large bags brought from builders merchants can contain as little as 850Kg

Posted: Sun Feb 20, 2011 8:11 am
by Dave_L
Also depends what you're hitting the subase with! Whacker plate or twin drum roller?

Posted: Sun Feb 20, 2011 2:57 pm
by rolysatch
thanks for all the advice, its a whacker plate i'm going to be using.