Page 1 of 1

Posted: Wed Apr 22, 2009 8:52 pm
by richie_jones
Digging out was hard Graft!!!!

Image
Image
Small retaining wall built

Image
Image

Linear drain channel..

Image


Sub base going in after whacking soil....
Image
Image

Thanks for all the advice guys, hopefully be laying the sandstone on friday....

Posted: Wed Apr 22, 2009 11:00 pm
by lutonlagerlout
looking good rich,nice to see you are using lines
LLL :)

Posted: Sun May 03, 2009 9:14 am
by Tony McC
So: did you ever get the paving laid?

Posted: Mon May 04, 2009 6:50 pm
by richie_jones
Due to the bad weather the projects slightly delaid....

Circle feature was more difficult than i expected as i`m not happy with all the joint lines. I wish i`d started with the center stone first but wasn`t confident enough with my setting out.

Image

Image

The Paving maul in the background caused the death of a 600x900 flag...It looked smaller on the website....

Image

Image

I`m thinking of tidying the joints up with the grinder just to even them out a bit..

Image

Just waiting for the sunshine now...

Posted: Mon May 04, 2009 7:07 pm
by msh paving
Looks good ,no probs there for first time job,i would no advise to trim the slabs to sort out the lines unless you are very confident with a disc cutter

Nice to see you using good quality tools, very nice MSH :)

Posted: Mon May 04, 2009 7:35 pm
by richie_jones
Thanks for the comments:

I`ve purchased rompex easy for the jointing but didn`t realise that they recommend 30mm joint depth, mine mostly are 10-20mm. Pavings been down for a week now so scraping these out will be a problem. Maybe after scraping out i might be able to nudge the circle feauture around a bit to even out the joints.
Grinder hopefully last resort...

Posted: Mon May 04, 2009 9:10 pm
by msh paving
Chances are if you nudge it will rock,speak to Romex Ray 07872824010 about the joint depth before you go to mad on scraping out he will advise you best MSH :)