For scheduling purposes, how long
would you estimate it would take one man
to install 100 m2 of 10 x 10 x 10 cm granite setts
(flexible method). This assumes the sub grade, base
and bedding layer are down and compacted,
and everything is ready to go.

Nothing fancy, not even fan patterns, etc.

Just a ballpark estimate is fine, I wont hold you to it!

Thanks

Posted: Sat Jun 03, 2006 6:48 pm
by Tony McC
2-4 days, depending on how experienced he is.

And normally, a sett mason wouldn't be working on his (or her) own. They'd need at least one labourer.