Grinding concrete - Good concrete finish by grinding

Setts and cobbles, tarmac, asphalt, resin systems, concrete whether it's plain, patterned or stencilled, gravels, etc.
Post Reply
dan555
Posts: 9
Joined: Thu May 11, 2006 9:20 pm
Location: Lancs.

Post: # 12076Post dan555

I'm considering skimming over my concrete drive area with a 5 inch diamond disc grinder / planer. ( lot of tight corners so small disc probably best)
I,ve recently laid about 30sq. meteres and will be laying another 10sq. meters next week.
I didn't get a good fnish and a few high spots so I'm hoping to smooth it out and leave the same finish throughout.
Would it be better to grind within a week of laying the concrete or let it fully cure for a month?
D Brown

Tony McC
Site Admin
Posts: 8346
Joined: Mon Jul 05, 2004 7:27 pm
Location: Warrington, People's Republic of South Lancashire
Contact:

Post: # 12090Post Tony McC

Are you grinding to achieve a finish or to remove high spots with the intention of laying a new surface layer over the lot? For a good finish, you need to allow the concrete to cure for at least 14 days, preferably 28, but if it's just a slavage operation, grind asap as it will be much easier, and even if the resultant surface is ragged, the eventual new surface layer will hide all the faults....hopefully.
Site Agent - Pavingexpert

dan555
Posts: 9
Joined: Thu May 11, 2006 9:20 pm
Location: Lancs.

Post: # 12114Post dan555

Thanks Tony
I'm hoping to get a good finish so I'll let it cure.

Because I'm not taking much off I doubt it will get rid of the 1mm wide crack around the perimeter of every bay.
What's the best way to fill cracks?

Regards
D Brown

Tony McC
Site Admin
Posts: 8346
Joined: Mon Jul 05, 2004 7:27 pm
Location: Warrington, People's Republic of South Lancashire
Contact:

Post: # 12135Post Tony McC

There isn't a "best way". Leave it to nature.
Site Agent - Pavingexpert

Post Reply