wondered if you guys can give me some advice, I'm doing a garage base, 29' x 10'.

Ive done the shuttering and put down and compacted the crusher run, which i think is all OK,

The thing that worries me, is that when i see pictures of the tramping being done, there are always two people doing it, one on either side of the slab,

but this base is right next to a fence, so that wont be poss,

i wondered if the solution would be to divide the slab up into say 4' sections if you see what i mean, might make it easier..

this is the first time ive dont anything like this , so please excuse my ignorance..

i'll see if i can post a picture..

ps..i know one solution would be to remove the fence the panels, but i'd rather not, difficult neighbour, lol

thanks in advance...jeff




hmmm...cant seem to work out how to post a pic
:(

Posted: Sun Dec 17, 2006 3:38 pm
by jeff wood
www.magix-photos.com/permamedia?exportc ... A651B35D18


Ok, if you copy and paste, thats where ive stored a picture...

Posted: Sun Dec 17, 2006 4:12 pm
by MatthewWakeman
jeff

shuttering looks fine looks like its a pair of wellies for the man on the right.

regards
matthew

drivewaycompany.co.uk

Posted: Sun Dec 17, 2006 5:09 pm
by jeff wood
Thanks Matthew !

And do you think I should divide the slab anyway, maybe into 3 sections, or just do it in one go ?

Also...I know a builder who said he would come and help do the tamping, as to be honest i'm a bit nervous about that part, visions of me buggering it all up..

But he can never seem to spare the time, and im worried that the weather will get too cold, plus the garage company ( pudsey) are snapping at my heels because they want to deliver the garage....

So , Should i attempt it on my own, well my father in law will help, or should i wait till i can get expert help ??


hmmm

Posted: Sun Dec 17, 2006 8:27 pm
by seanandruby
you could divide slab to coincide with movement joints. no need to take down the fence just tamp as close as you can then take footprints out with a t tamp which takes 5 minutes to make. thing is not to panic. and dont forget the membrane

Posted: Mon Dec 18, 2006 12:18 am
by jeff wood
thanks for your advice...

so how many divisions do you think i should make, its 29' length and 10'6"" width....