Posted: Mon May 08, 2006 4:01 pm
by deckertelford
just quoting for 100 sq. m of trvertine and getting conflicting advice on which base (concrete or screed) and butt joints or pointed joints. all help gratefully recieved
pete ???
Posted: Tue May 16, 2006 9:38 pm
by Tony McC
10:1 semi-dry or moist mix for the laying course. Screed it if the Travertine is of a regular thickness. The choice between mortar-pointed joints and sand-filled butt-joints is one of aesthetics. If this was a well-worn Travertine, I'd probably go with butt-joints.
Posted: Wed May 17, 2006 9:11 pm
by deckertelford
cheers pal can you fix the weather now..........
Posted: Thu May 18, 2006 9:05 pm
by Tony McC
Yep...just give me a few days!