Posted: Sun Apr 16, 2006 1:32 pm
by shaneJ
Hello, I intend to use a bedding layer 40mm of sand/cement at 10:1 on top of compacted hardcore. The area is 32m2. My question is will I have to lay the slabs onto the bed layer straight away? I am working by myself and I am not sure I will be able to complete in one go. Would it be possible to lay a bedding layer of say 30mm one weekend and then the following weekend individualy bed slabs onto 10mm.
Please be gentle.

Posted: Wed Apr 19, 2006 9:51 am
by Tony McC
Just lay out as much bedding as you can cover in an hour or so. There's no need to mix all the bedding in one go.