Posted: Mon Oct 17, 2005 1:15 pm
Firstly I'd just like to compliment you on a very good and informative webite.
This is my first attempt at anything like this so I apologise in advance if my questions appear basic.
I am laying a small patio (4m by 3.5m) using 450 x 450 x 32mm slabs. I have done the excavation so I am now at the exciting part and would like some clarification if possible.
1. I am going to put down 10:1 sharp sand and cement as suggested but in a couple of places on the website you refer to this as semi dry. Are you saying I have to add water to the 10:1 mix? If so how much?
2. Once I have put the sand\cement down I will then compact it with a hired compactor. Once I have done that do I add another layer or do I then screed the compacted layer?
3. How long have I got after laying the sand to get the slabs down. Not being an expert I'm worried that I will put all the sand down but not have time in the same day to screed and lay all the slabs.
Thanks in advance for your help.
This is my first attempt at anything like this so I apologise in advance if my questions appear basic.
I am laying a small patio (4m by 3.5m) using 450 x 450 x 32mm slabs. I have done the excavation so I am now at the exciting part and would like some clarification if possible.
1. I am going to put down 10:1 sharp sand and cement as suggested but in a couple of places on the website you refer to this as semi dry. Are you saying I have to add water to the 10:1 mix? If so how much?
2. Once I have put the sand\cement down I will then compact it with a hired compactor. Once I have done that do I add another layer or do I then screed the compacted layer?
3. How long have I got after laying the sand to get the slabs down. Not being an expert I'm worried that I will put all the sand down but not have time in the same day to screed and lay all the slabs.
Thanks in advance for your help.