I am currently laying yorkstone setts on my drive from a delivery I received late last year, I ordered an initial 30 sqms. The block size is 200x100mm.
I have now figured out that there is not 30sqm. Checking my emails I see that I've been quoted 43 blocks to the sqm. At the time I just went off the SQM x price. But now realise I am 210 blocks short on this order. This based upon 50 blocks to the sqm. I have also laid the same size granite setts but these are quoted at 50 to the sqm.
I went back to the supplier yesterday who said that is what they quote 43 to the SQM. To me that is not a SQM. It's 86% of a SQM.
My question is, is this normal in the trade, and am I paying for the gaps between the setts, either way it does not appear to be correct. Sell to the sqm then supply less than a sqm?
Advice would be appreciated.
Thanks
Graham
I am currently laying yorkstone setts on my drive from a delivery I received late last year, I ordered an initial 30 sqms. The block size is 200x100mm.
I have now figured out that there is not 30sqm. Checking my emails I see that I've been quoted 43 blocks to the sqm. At the time I just went off the SQM x price. But now realise I am 210 blocks short on this order. This based upon 50 blocks to the sqm. I have also laid the same size granite setts but these are quoted at 50 to the sqm.
I went back to the supplier yesterday who said that is what they quote 43 to the SQM. To me that is not a SQM. It's 86% of a SQM.
My question is, is this normal in the trade, and am I paying for the gaps between the setts, either way it does not appear to be correct. Sell to the sqm then supply less than a sqm?
Advice would be appreciated.