Hi all
Just like to say this is a fantastic website !!!
I recently recieved a quote of £2175 to supply and fit 80mts of standard brindle majority of digging has been completed
Does this price sound right
I calculated
8 ton of MOT
8 ton of grit sand and the block to cover 80 meters
Cost for foundation would be approx £540
Any help is appreciated
Thanks
Aaron
Posted: Sat Mar 17, 2012 1:54 pm
by local patios and driveway
Get three quotes always. Seeing as the blocks will be about a grand, the sand and stone about 650.. I cant see anyone laying 80mtrs for a few hundred quid. Run a mile
Posted: Sat Mar 17, 2012 3:43 pm
by haggistini
who was the quote from?
Posted: Sat Mar 17, 2012 4:58 pm
by aaron2788
I Got quote from a company based in Bolton...The qiote was £2175 supply and fit 30meters in Brindle..
My calculations are
3 Ton MOT
2 Ton Sand
3 pack of Brindle block
3 covers for Inspection Chambers
Cost for materials would be approx £550.00
Just seems to be quite exspenive for the labour if materials are only £550.00 unless this is a 2-3 week job
The ground is ready for MOT..So no digging required
Posted: Sat Mar 17, 2012 8:31 pm
by local patios and driveway
80 or 30, now im just confused if i was to price 30 it you would have to pay £1950 assuming no drainage or ic covers etc
Posted: Sat Mar 17, 2012 8:50 pm
by aaron2788
Hi
Sorry for the confusion it is 30 meters if materials are £550 seems a lot for Labour ?? How long would this normally take? Yes there is 3 IC
Thanks mate
Posted: Sat Mar 17, 2012 10:18 pm
by Carberry
9T of type one at 150mm - £270
2T of sharp sand - £60
3 packs of blocks - £300 (more if they are marshalls)
3 recessed covers - £150
That's 780, round up to £800 when you include kiln dried sand and cement.
That leaves 1375 for labour.
Sounds about right assuming they do a proper job.
Posted: Sun Mar 18, 2012 9:20 am
by Dave_L
Are these inset covers? If so there is a lot of work in fitting/cutting these in.
Posted: Sun Mar 18, 2012 10:42 am
by aaron2788
Carberry wrote:9T of type one at 150mm - £270
2T of sharp sand - £60
3 packs of blocks - £300 (more if they are marshalls)
3 recessed covers - £150
That's 780, round up to £800 when you include kiln dried sand and cement.
That leaves 1375 for labour.
Sounds about right assuming they do a proper job.
Hi Dave
I was under the impression I would need 2 inch mot as this is only a patio area...150 seems a lot for a patio
Posted: Sun Mar 18, 2012 10:55 am
by Carberry
aaron2788 wrote:Carberry wrote:9T of type one at 150mm - £270
2T of sharp sand - £60
3 packs of blocks - £300 (more if they are marshalls)
3 recessed covers - £150
That's 780, round up to £800 when you include kiln dried sand and cement.
That leaves 1375 for labour.
Sounds about right assuming they do a proper job.
Hi Dave
I was under the impression I would need 2 inch mot as this is only a patio area...150 seems a lot for a patio
My mistake. that amount of MOT is for a driveway. for patio I would go 75mm minimum, so 4-5T.
Posted: Sun Mar 18, 2012 7:01 pm
by ken
I live and work in the Manchester area, I’ve just worked out what id charge, and the price you have been given is spot on. And its a 2-3 day job, not 2-3 weeks.