Posted: Thu Apr 28, 2011 9:58 am
In reading the website about inset manhole covers, it seems to suggest that after contructing most of the paving, the manhole cover is the last thing to be istalled to ensure the correct level with the rest of the paving.
However, my manhole is right at the edge of the driveway and will have to form part of my edging course and will therefore have to be installed first.
Has any one else had to do this first and were there any particular problems? Or any tips to ensure the correct level is achieved.
Thanks
Paul