Good morning.

Fantastic website - which I've studied for months now.

I may be about to be awarded "the stupid question of the day" award but here goes anyway!

I want to have a driveway installed, but I also need a dropped kerb put in - which should be done first?

Thanks.
Stuart.

Posted: Wed Mar 02, 2011 3:28 pm
by Pablo
it doesn't matter really but it would be ideal if the same company could do them both at the same time. I personally would do the kerb first it would make access easier for materials.

Posted: Wed Mar 02, 2011 7:07 pm
by ambient
if the drop kerb is being done by council highways around here, they wont do it till drive has been done

Posted: Thu Mar 03, 2011 1:33 pm
by stumac49
Thanks for the replies.

I've been told by one contractor to get the kerb done last, but then I've had 3 others tell me not to even bother getting it done as the kerb is so low anyway!

Thanks again.
Stu.

Posted: Thu Mar 03, 2011 8:24 pm
by Dave_L
I would tend to do the kerbing works last, as the tarmac will then be nice and new etc

Doing it first you'd have to lay some protection boarding down on the new surfacing as any plant trafficking over it will mark a freshly laid surface.

Posted: Thu Mar 03, 2011 9:32 pm
by seanandruby
i would put the dropper in first then you have something to work to, a picture frame.