Posted: Wed Oct 21, 2009 2:27 pm
Hi,
Sorry for the noob post.
I have recently replaced some of my front drive with type 1 crushed concrete (previously a muddy hill). I have plans to change this to block paving at some point in the future.
I was advised to use Type 1, but not advised of the change in the governments stance towards it. The planning permission website suggests that this is impermeable, and therefore I am assuming requires planning permission. However, everybody on here still advises to use it from what I can see.
Can I leave my drive as Type 1 (with no paving / tarmic on top for 6 months), or am I likely to have the council complaining?
Thanks
Sorry for the noob post.
I have recently replaced some of my front drive with type 1 crushed concrete (previously a muddy hill). I have plans to change this to block paving at some point in the future.
I was advised to use Type 1, but not advised of the change in the governments stance towards it. The planning permission website suggests that this is impermeable, and therefore I am assuming requires planning permission. However, everybody on here still advises to use it from what I can see.
Can I leave my drive as Type 1 (with no paving / tarmic on top for 6 months), or am I likely to have the council complaining?
Thanks