Posted: Sat Nov 05, 2005 1:52 pm
I have a contractor laying a new patio for me and I am concerned about the methods they are using.
They laid the patio a couple of weeks ago but the following week when we had heavy rain it flooded because the they did not provide drainage and also they didn't get their levels correct.
I made them lift the blocks and start again. They lifted the blocks, removed the sand layer and are now laying the blocks on a 50mm bed of 6mm gravel. I am rather concerned about this as I always thought sand was the correct medium.
They told me this is the modern method used by installers on building sites. At the moment they have laid the gravel, set their levels and coming first thing Monday morning to finish the work. They are also not doing any compacting of this gravel until after the blocks are laid.
I would appreciate anyone being able to give me some help on this quickly as I only have until Monday morning to decide whether I continue to let the contractors continue with this.
They laid the patio a couple of weeks ago but the following week when we had heavy rain it flooded because the they did not provide drainage and also they didn't get their levels correct.
I made them lift the blocks and start again. They lifted the blocks, removed the sand layer and are now laying the blocks on a 50mm bed of 6mm gravel. I am rather concerned about this as I always thought sand was the correct medium.
They told me this is the modern method used by installers on building sites. At the moment they have laid the gravel, set their levels and coming first thing Monday morning to finish the work. They are also not doing any compacting of this gravel until after the blocks are laid.
I would appreciate anyone being able to give me some help on this quickly as I only have until Monday morning to decide whether I continue to let the contractors continue with this.