I have just had a job completed, driveway. The finished job looks good. I chose the contractor with reference to other completed jobs and satisfied customer, written quote specified 100mm mot sub base, 40mm sand all compacted etc etc. The job was as specified and looks good. BUT...after refering to your site I notice that the blocks were not laid on cement but some cement was placed at the side of the blocks (a resonable amount 1 side but not a lot on the other as the block paving is close to the boundry).
I have not paid yet. I seek advice on how to proceed, considering that this aspect was not detailed in the quote.
If I were to insist on it being rectified how much work is now involved? What can I quote to strengthen my case? If he refuses to correct it what other options are available to me? Could I get someone else to correct it and pay them? Or would it be best to leave it and see if it is OK?
Thanks
Help please - Job just completed
-
- Posts: 106
- Joined: Mon Jul 07, 2003 3:07 pm
-
- Posts: 106
- Joined: Mon Jul 07, 2003 3:07 pm
Make sure he lays the edge pavers on a bed at least 100mm deep and the hauncing comes two thirds up the side of the edging paver.
The drop of sand level in the gaps is normal. When it has been dry for a few days, the contractor should either come back and top up the sand or leave you a bag so you can do it your self.
Cheers Carl
The drop of sand level in the gaps is normal. When it has been dry for a few days, the contractor should either come back and top up the sand or leave you a bag so you can do it your self.