Page 1 of 1

Posted: Wed Jul 31, 2013 9:09 pm
by prc76
Hello All

Apologies if this question has already been asked and answered elsewhere in the forum; a brief search didn't reveal anything.

Background:

I'm planning to install a new driveway across a field: the drive will be about 160m long x 3m wide, with a parking/turning area at the end. Total area about 800 sq. m. The route for the drive is generally level (perhaps a gradual slope down between entrance and turning area), with some undulations. Location: Derbyshire.

The installation of the drive will enable renovation/building work on a building at the end of the drive. After the building work is complete, the finished surface will be applied to the drive. The intention is to use a self-binding gravel for the finished surface (e.g. Breedon but without the Breedon price tag!). The recommendation for that seems to be 50mm compacted depth.

The sub-base will be 150mm compacted depth (compaction using a vibrating roller as described on the PE site - but don't know weight of roller yet to determine no. of passes ...).

So the plan is to dig out at least 200mm deep, apply a layer of Terram 1000, install the sub-base (Type 1) and use that during the building work. Spoil from digging out will be distributed around the field - there are plenty of large hollows that can be filled.

After all that the question is, I hope, simple: approximately how much per sq. m could I expect to pay to have a sub-base installed as described above by a competent contractor (excluding cost of Type 1)? Assume no spoil removal necessary.

I realise that's probably impossible to answer this question properly without seeing the site. However, any ballpark figures based on experience are greatly appreciated.

Thanks in advance!

Posted: Wed Jul 31, 2013 10:12 pm
by lutonlagerlout
oww-ahh

assuming good access for say a 5 tonne machine and 2 3 tonne dumpers
and no muck away costs around £15k

you have a lot of type 1 to go in there,maybe 150 tonnes also


if you have 8 wheelers going in for the building work i would go deeper on the drive =/- 300 mm deep

maybe used hardcore or summat cheaper on the bottom 150mm and top with type 1

just a ballpark figure mind
LLL

Posted: Thu Aug 01, 2013 10:56 am
by TheRockConcreting
Personaly i would hire that temporary road sheeting they are using on the big solar farms now, then do the driveway to the proper spec and consider a decorative driveway such as an Exposed Aggregate Concrete Driveway to blend in with the surroundings.