Page 1 of 1
Posted: Wed Oct 30, 2002 4:28 pm
by 66-1093879036
Hi,
I am planning to lay paving blocks over an 18 square meter drive. I have the base complete and need to know how much grit sand to order for the bedding layer and how much silica sand I will need to brush down the gaps.
Cheers.
Posted: Wed Oct 30, 2002 5:09 pm
by 84-1093879891
2 tonnes of grit sand and 2 bags of the jointing sand (40kg bags) should do it.
There's a spreadsheet for calculating all these quantities on the Laying Blocks page. :)
Posted: Wed Oct 30, 2002 10:11 pm
by 66-1093879036
Thanks Tony,
I will get on to my local merchant.
One thing I have noticed with todays heavy rain, there is a shallow puddle slightly off from center. It's about half an inch deep and about the size of a flagstone but if it gets any deeper it will drain off the edge. Is this a problem or am I ok to lay the bedding sand and blocks?
Posted: Thu Oct 31, 2002 12:02 am
by 84-1093879891
I take it this is a puddle on the base that you intend to pave over? If so, don't worry about it - chase out any standing water with a yard brush before placing and preparing the laying course, just so it doesn't get saturated. :)
Posted: Thu Oct 31, 2002 10:55 pm
by 66-1093879036
Cheers Tony,
I seems I've been a bit thick as I was assuming that surface water drains between the blocks through the sand then runs off the concrete base at the edge. Thats why I was worried about failing to get the base to drain properly as I was imagining a permanent puddle under the blocks. Obviously I just need to make sure the the blocks are set so they drain where I want.
Thanks again.
Posted: Fri Nov 01, 2002 12:01 am
by 84-1093879891
It's not just you - it's a common misconception that surface water drains through the joints of a block pavement when, in fact, over 98% of surface water never gets more than 3mm into the surface of the pavement. Howver, the laying course still needs to drain, so it's good practice to ensure you're not creating a 'pond' beneath the pavement. :)