Posted: Tue Apr 19, 2011 8:52 pm
by ilovesettsonmondays
rang round this afternoon for a mini digger for one day next week . got one for 180 for the day in the end . worst price 350 for the day . dick turpin diggers i think they called themselves

Posted: Tue Apr 19, 2011 9:24 pm
by Dave_L
Sure that second quote wasn't machine and driver??

Posted: Tue Apr 19, 2011 9:28 pm
by dig dug dan
If its any help, i put me and my digger out for £230+vat.
It does come with some attachments that you cannot hire elsewhere though.
£180 for just a digger is a little steep

Posted: Tue Apr 19, 2011 9:32 pm
by ilovesettsonmondays
it was dave . so was the 180 pound one . i had one last week with driver for 150 . he booked up now. around the essex area 200 quid about the norm.

Posted: Tue Apr 19, 2011 9:32 pm
by Carberry
Got some quotes last week for digger hire, £160 for the week was cheapest.

Posted: Tue Apr 19, 2011 9:38 pm
by GB_Groundworks
we go roughly with tonnage for 1 man and machine, dumpers breakers augers post driver, rollers extra etc

1.5 - 3 ton £250
8 ton/3cx/telehander/4x4 tractor+trailer or attachments £450
13/16 ton £550 and delivery/removal
5 ton tracked dumper £100 a day
1/3/6 ton dumpers as per job
muck shifted for £8/ton

but like to go with 2 guys as get lot more done so adds £100 more to it but get lot more done and better do do full job than day rate

dont hire out machines no one treats them like you do,

local hire shop is about £150 a day for 2 tonner




Edited By GB_Groundworks on 1303245594

Posted: Tue Apr 19, 2011 9:45 pm
by Dave_L
Still....a 5 ton machine and a decent operator for £350/day is a gift IMO given the amount of work you'd get out of the combination and not to mention the haulage of said machine to and from site.......

Posted: Tue Apr 19, 2011 10:29 pm
by GB_Groundworks
yeah these lads with just a mini for 150 a day, compare that to 350 for a 5 ton and you'd get 10x the work done if the works there,

we did a job the other week were theyy'd had a guy in with a mini but ran out of dig depth had to get us in with a bigger machine to finish the job for them