Page 130 of 315
Posted: Wed Jul 11, 2012 11:02 pm
by Thepinkpavingco
Doesn't look like we have done a lot but no one ever appreciates the groundworkers
Posted: Wed Jul 11, 2012 11:27 pm
by lutonlagerlout
nice work
why the telescopic vents so long?
I wish our groundworkers were as neat as you lot :;):
did anyone get the black man's pinch doing the blocks between the beams?
LLL
Posted: Thu Jul 12, 2012 6:28 am
by mickg
nice detail with the driveway Danny and nice job with the foundation too
Posted: Thu Jul 12, 2012 9:03 am
by Thepinkpavingco
Cheers mick
Posted: Thu Jul 12, 2012 7:06 pm
by dig dug dan
Posted: Thu Jul 12, 2012 7:08 pm
by dig dug dan
Posted: Thu Jul 12, 2012 7:19 pm
by lutonlagerlout
nice bricks dan !!
i wonder where they came from
you did very well in 3 days
we had to cover brickwork 7 times yesterday due to sudden showers
PITA
today was a nice day,got scaffold high but no pics as banging the bricks down
i would have thought more like a week for that job if pricing,but looks like the slabs etc came up easy
happy days
LLL
Posted: Thu Jul 12, 2012 8:15 pm
by dig dug dan
i think also the safety inlet gate was removed too!
1pm concrete pour booked today, turned up at 4.40! left the site at 6.30, but luckily dumper soon made short work of bringing the concrete round.
back mid august for slabs.
Posted: Thu Jul 12, 2012 8:32 pm
by msh paving
Posted: Thu Jul 12, 2012 9:22 pm
by rab1
mark, you forgot the revelent task specific risk/meathod statement. :;):
Posted: Thu Jul 12, 2012 10:38 pm
by London Stone Paving
We've gone risk assesment crazy down at London Stone. Since moving to our new HQ I have had to carry out approx 30 risk assesemnt's, most of the stuff is common sense but it has definately raised the standards of H&S at our place.
Nice work there Dan. Its really good to see stuff being reused on site. Our crusher was going great guns until the last couple of weeks. The belt has started to slip to the right before eventually jamming. We've done a bit of welding on it today, so hopefully it should be sorted. Great machine though. We' started shifting the stuff at £5 per ton to get it moving. Then it all moved very quickly, so gonna put it up to £10 per ton and see how it goes. The local pikies are going crazy for it
Posted: Fri Jul 13, 2012 1:20 am
by mickg
nice detail with the semi circle Dan