Posted: Fri Sep 16, 2016 11:06 am
Thanks All - A slow worker, but I get there in the end (not helped by being sick for the last 3 days, and a downpour of rain filling the hole!).
I now have a trench slightly larger than before - but minus the pipe. So, it now looks like a 'T', with the width of 500mm, a depth of just over 500mm, with the width of the bottom part around 120mm.
A few final questions, if I may?
Fill with a mix of ballast:cement:water with a mix of 6:1:0.6 by volume? Or more ballast? (Why?)
Do I line the trench with DPM first?
As I have a delivery of rebar due early next week, does anyone have any tips about how I best lay this out?
Is there anything else that I have missed? Or should I be good to mix and fill? Any other tips?
A million thanks everyone.
I now have a trench slightly larger than before - but minus the pipe. So, it now looks like a 'T', with the width of 500mm, a depth of just over 500mm, with the width of the bottom part around 120mm.
A few final questions, if I may?
Fill with a mix of ballast:cement:water with a mix of 6:1:0.6 by volume? Or more ballast? (Why?)
Do I line the trench with DPM first?
As I have a delivery of rebar due early next week, does anyone have any tips about how I best lay this out?
Is there anything else that I have missed? Or should I be good to mix and fill? Any other tips?
A million thanks everyone.