Page 2 of 3

Posted: Wed Jun 13, 2007 8:28 pm
by The-oracle
They are Riven slabs. Bought from Wickes and supplied directly by Marshalls. Sizes varry between 860 x 560 and
560 x 560 and 560 x 270 and 250 x 250

Posted: Wed Jun 13, 2007 8:57 pm
by lutonlagerlout
sorry for the confusion
riven SLABS are made from concrete
riven FLAGS which is what you have are natural stone
did he use any subbase under the sand cement bed~?
i.e. hardcore or type 1 stone?
cheers LLL

Posted: Wed Jun 13, 2007 11:34 pm
by The-oracle
lutonlagerlout wrote:did he use any subbase under the sand cement bed~?
i.e. hardcore or type 1 stone?
cheers LLL
NO none

He laid straight on the sand & Cement bed :angry:

Is it essential to have an MOT1 under stones?

Posted: Thu Jun 14, 2007 12:44 am
by Suggers
Yeah - but what did he lay the bedding mix onto? - levelled, compacted subsoil - you must have seen it?
ps - I'm with LLL on this one, don't do anything rash -

Posted: Thu Jun 14, 2007 9:50 am
by The-oracle
He laid it straight on the soil (he compacted the soil after taking out all the vegetations).

Posted: Sun Jun 17, 2007 2:57 pm
by The-oracle
Just to update you guys
I got a pro to redo the job now.

He removed all the slabs, cleaned them, digged out the previous bedding, laid 25mm of MOT Type1 subbase & compacted it. Tomorrow he'll lay the patio on a Sharp sand & cement mix (semi-wet mix), then he'll do the bonding at a latter stage.

He is charging £800 for a 24m2 area (not sure if the price is right, but I feel like he knows his stuff and he's listed on the Marshall's website as one of their recommended contractors).

The work also includes replacing a manhole with a recessed one filled with flags and laying and compacting 25mm of MOT type1 subbase over another 20m2 in preparation of laying some artificial grass.

Your thoughts please

Posted: Sun Jun 17, 2007 8:13 pm
by lutonlagerlout
whats the point of 25 mm of MOT type 1?
none
needs to be dug out and 100mm compacted type 1 installed
LLL

Posted: Sun Jun 17, 2007 10:02 pm
by The-oracle
OMG I am sorry
It is indeed 100mm, I need to go back to math school

I brought in 5 tonnes of M.O.T Type1 for a 24m2

Posted: Sun Jun 17, 2007 11:09 pm
by lutonlagerlout
5 tonnes bit on the low side for that,24m2 needs about 8-10 tonne to get 100mm thick
LLL :)

Posted: Mon Jun 18, 2007 9:23 am
by The-oracle
lutonlagerlout wrote:5 tonnes bit on the low side for that,24m2 needs about 8-10 tonne to get 100mm thick
LLL :)

Not according to the Calculator on this site

I used it as aguide as to what to order, and it told me go buy 4.8 Tonnes

Posted: Mon Jun 18, 2007 4:28 pm
by Rich H
Bang on. Although, I work on 1tonne/7 sq.m at ~70mm depth which is all you really need for a sub-base for domestic paving. 100mm + 50mm (or so) sharp+cement + 50mm (or so!) slab = 8 inches of solid stuff. Surely OTT for a back garden job?

Posted: Mon Jun 18, 2007 5:18 pm
by lutonlagerlout
sorry oracle
looks like i completely lost the plot there?
it is indeed about 5 tonnes
i havent got a danny where i got 8-10 from
??? ??? ???
ahem
LLL

Posted: Mon Jun 18, 2007 8:39 pm
by The-oracle
lutonlagerlout wrote:sorry oracle
looks like i completely lost the plot there?
it is indeed about 5 tonnes
i havent got a danny where i got 8-10 from
??? ??? ???
ahem
LLL

lutonlagerlout
I got my math wrong myself when I suggested a 20mm subbase :;):

And Rich H you are right, even the 5 tonnes did not get me the 100mm, I got circa 80mm after compaction with a wacker, which is - as you said - enough for a rea patio.

Posted: Mon Jun 18, 2007 10:36 pm
by Stuarty
Remember you wont ever get a tonne from a merchants, in the bulk bags anyway. You order 5 bags and your about a half tonne to three quarter shy in weight

Posted: Mon Jun 18, 2007 10:37 pm
by lutonlagerlout
i'm pretty sure minimum subbase is supposed to be 100 mm when compacted,but in the real world of barbecues and kids playing its unlikely to move, and is a damn sight better than no subbase at all
sounds like your on the right track now mate
good luck
LLL :)