My house was built in 1906 and has a 3 brick deep brick skirt which has always been hidden by soil. The top brick is 80mm below the damp course. My question is, where should my block paving be? If I sit it on top of the top brick then I have only 30mm gap beneath it and my damp proof. Do I lay them on the second brick down and expose the first layer of brick skirt? Or do I lay it level with the damp course in the same place as where the soil has always been?

Many thanks in advance.

lutonlagerlout
Site Admin
Posts: 15184
Joined: Fri Aug 04, 2006 12:20 am
Location: bedfordshire

Post: # 99431Post lutonlagerlout

on old houses generally 150mm below finished floor level will work
without actually seeing it its impossible to say 100%
LLL
"what,you want paying today??"

YOUR TEXT GOES HERE

Cmsajon1
Posts: 3
Joined: Sat Jun 14, 2014 10:47 pm
Location: Liverpool

Post: # 99442Post Cmsajon1

Thanks. My finished flooring is around 300mm above the damp course (out of picture, its about 4 red bricks above damp course).

To better describe what I mean I've included the picture below. As you can see, I have the decorate red brick I don't want to cover. Then the damp course, then 3 levels of foundation brick, with the first brick being flush with the red brick.

Do I lay my block paving level with damp course? If I lay it lower I'm exposing the brick foundations which are quite ugly and have always been covered with soil.


Thanks

Image
Alex jones

sy76uk
Posts: 791
Joined: Wed Feb 05, 2014 7:50 pm
Location: leicester

Post: # 99447Post sy76uk

You should be safe 2 courses below your air brick.

Cmsajon1
Posts: 3
Joined: Sat Jun 14, 2014 10:47 pm
Location: Liverpool

Post: # 99492Post Cmsajon1

sy76uk wrote:You should be safe 2 courses below your air brick.
Would the first line of bricks below the red brick be left visible then?

Thanks
Alex jones

sy76uk
Posts: 791
Joined: Wed Feb 05, 2014 7:50 pm
Location: leicester

Post: # 99507Post sy76uk

Yes. I always tend to go around 4-6" below inside finished floor level.