Spongy ground a nightmare

All forms of block paving, brick paving, flexible or rigid, concrete or clays, new construction or renovation
rab1
Posts: 1869
Joined: Sun Jun 07, 2009 10:19 pm
Location: scotland

Post: # 94981Post rab1

Its actually been a good winter up here, wet but no wetter than normal (think pissing down most days but no snow)
God loves a tryer

williams
Posts: 166
Joined: Sun Mar 16, 2008 6:01 pm
Location: essex

Post: # 95119Post williams

Ok it's happened again :(

Dug the job out and actually covered it all up with a tarp because I knew heavy rain was coming. Went in today, took tarp off, ground was a. Bit wet but not too bad.

Type one delivered, spread it and felt ok underfoot, compacted it just once and it's was like a blancmange! Worst I've ever seen in my life.

So it appears it's not the ground it's the soaking wet stone that's being delivered. Spoke to the bloke who does me the stuff and he's using it as well as they also have a paving company, when asked how they get round it he told me they just crack on!
I'm not exaggerating it's like jelly!

It's just 25m so went and got 11 bags of dust and hand mixed it all into the type one and it appears to have dried it out enough. I have left it needing to be topped up by about 75mm so hopefully will be ok now.
Covered it again tonight as the rain was silly so hopefully tomorrow it will be solid.

Honestly never had these problems before :(

GB_Groundworks
Site Admin
Posts: 4420
Joined: Sat Aug 09, 2008 3:55 pm
Location: high peak
Contact:

Post: # 95124Post GB_Groundworks

change your agg supplier, piss wet through mot is no good, goes thixotropic with vibration
Giles

Groundworks and Equestrian specialists, prestige new builds and sports pitches. High Peak, Cheshire, South Yorkshire area.

http://www.gbgroundworks.com

Kuts
Posts: 307
Joined: Sat Mar 26, 2011 5:34 pm
Location: Grrrrrr

Post: # 95125Post Kuts

try your bitmac supplier/local plant, i get mot cheaper than the recycled shite.

cookiewales
Posts: 1270
Joined: Mon Aug 10, 2009 8:30 am
Location: york work anywhere where the stone takes me
Contact:

Post: # 95126Post cookiewales

in the wet use lean mix am starting a job in ashstead surrey soon 180m2 setts ground clay 18m3 lean mix £1800 keeps site clean as well :D
Originalstonepaving.com

The very best in natural stone paving in new and reclaimed materials
M: 07968 582231

lemoncurd1702
Posts: 712
Joined: Sat Oct 19, 2013 7:56 am
Location: South Wales
Contact:

Post: # 95127Post lemoncurd1702

I've commented on this in the thread to "wet for block paving". Spread cement dust over the first layer of compacted base, final layer more cement and then compact. The cement from the first layer pumps up during compaction. It's not so much to make the base stronger, though it does also have this effect, but the introduction of cement dries the base material. I would also dust the sub-grade if not using terram.
You can also rotavate cement into the base before compaction but don't make concrete.

I've never tried this but apparently lime (specifically quicklime) applied to the sub-grade will dry the soil, maybe it would do the same for a sub-base.

Another method is to use clean 40mm and compact stone dust into it, do this in layers.

If your base is already down keep compacting it to bring the water to the surface brush the water to the lowest point or if your lucky the sun may shine. Regardless of the weather the base will eventually stiffen and I would go as far to say that it will be a better base than one done in the dry.
Cheers
Lemoncurd

Tony McC
Site Admin
Posts: 8346
Joined: Mon Jul 05, 2004 7:27 pm
Location: Warrington, People's Republic of South Lancashire
Contact:

Post: # 95130Post Tony McC

williams wrote:it's the soaking wet stone that's being delivered
There is a limit on the moisture content for Type 1 to be compliant. If they are delivering sodeen aggregate, refuse delivery on the grounds that it is outside the moisture content parameters of the spec.

Obv, the wagon driver will pull his face, but the stone is no use to you in that condition - he might as well deliver putty!
Site Agent - Pavingexpert

Tony McC
Site Admin
Posts: 8346
Joined: Mon Jul 05, 2004 7:27 pm
Location: Warrington, People's Republic of South Lancashire
Contact:

Post: # 95131Post Tony McC

lemoncurd1702 wrote:Spread cement dust over the first layer of compacted base, final layer more cement and then compact. The cement from the first layer pumps up during compaction.
You have to be wary of reducing the permeability of the sub-base. If the sub-base becomes less free-draining, it could result in the laying course becoming saturated which, in turn, causes liquefaction and movement of the block surface.

And you need to be ultra-wary about 'pumping'. If there is *any* risk whatsoever of pumping sub-grade material into the base, even if it is accompanying the cement, it could cause more problems with drainage and introduce a structural weakness.
Site Agent - Pavingexpert

lemoncurd1702
Posts: 712
Joined: Sat Oct 19, 2013 7:56 am
Location: South Wales
Contact:

Post: # 95136Post lemoncurd1702

Yeah I understand this Tony I've seen what happens to blocks laid on a concrete base.
I'm not trying to make an inflexible base I don' chuck that much cement at it, just enough to move the job forward. It may reduce permeability a little but not significantly enough to cause problems. Nothing has come back to bite me on the butt as yet.

Any thoughts on a no fines concrete or permeable bitmac with a terram layer to separate the laying sand.
Cheers
Lemoncurd

williams
Posts: 166
Joined: Sun Mar 16, 2008 6:01 pm
Location: essex

Post: # 95151Post williams

The problem here in Essex is that a plant closed down, think it was one beginning with a b?
Anyway all the stone now comes from the same place afaik. All the places I know have this stone, the only other option is crushed which generally is not all that, I have seen some nice stuff but more often than not it's got that muddy dirty smell, I'm convinced it's mud....

Makes life very difficult.

Anyway, went in today and it was fine, put another layer of type one on top and it's perfect (thank god).

I would imagine that 2 bags per ton isn't turning the base into a concrete base, that's something like a 11:1 mix I reckon.

williams
Posts: 166
Joined: Sun Mar 16, 2008 6:01 pm
Location: essex

Post: # 95152Post williams

That said it was bloody hard work knocking up 6 ton of compacted base with 11 dust :0

The idea of doing a layer, chucking some dust down, then another layer sounds quite reasonable though, ultimately all you want the dust to do is take up the wetness of it really.

lutonlagerlout
Site Admin
Posts: 15184
Joined: Fri Aug 04, 2006 12:20 am
Location: bedfordshire

Post: # 95159Post lutonlagerlout

in fairness one of the best block pavers i ever saw "tom togher" before his truck got wiped out by an artic on the motorway
always used 12:1 dry leanmix as a sub base
theres a drive near me he did 15 years ago and its still true today
i dont know the physics of it but it worked for him for years
LLL

PS he has the allotment next to me now and I didnt recognise him for 3 years,only when i saw an ultrascape bucket we got chatting
isnt that mad?
"what,you want paying today??"

YOUR TEXT GOES HERE

Tony McC
Site Admin
Posts: 8346
Joined: Mon Jul 05, 2004 7:27 pm
Location: Warrington, People's Republic of South Lancashire
Contact:

Post: # 95161Post Tony McC

No fines is a well-understood construction and is one of the recommended methods for permeable paving, but there's nowt to stop it being used for conventional paving. I'd certainly prefer it to permeable mac, which I still think is over-priced.

The only real concern I would have with a no-fines base in place of a flexible/unbound sub-base is that sodding geotextile to prevent trickle-down. I've seen what happens when geotextiles create slip and it scares me. Admittedly, it's an unlikely scenario on a driveway, but I wish there was some other way.