Rigid Vs Flexible block paving
I have been asking for quotes to convert our front lawn (50 sq. m) into a driveway. After getting a few ridiculous quotes (e.g. £6800 !), I have now got a attractive quote for labour costs (£ 900 for about 3 days work). But the guy has experience of doing rigid paving (blocks on concrete rather than crushed stone). The material cost for this rigid paving is coming around to £1000. So basically the entire driveway will be done under two grand.
But what I am not sure is if rigid driveway inferior to flexible driveway in any way e.g. quality, longevity etc ...
Any experiences, knowledge will be highly appreciated.
Thanks,
Krish.
Edited By GB_Groundworks on 1368598904
Rigid vs flexible block paving
-
- Site Admin
- Posts: 4713
- Joined: Mon Jun 26, 2006 11:01 am
- Location: eastbourne
-
- Site Admin
- Posts: 15184
- Joined: Fri Aug 04, 2006 12:20 am
- Location: bedfordshire
-
- Site Admin
- Posts: 15184
- Joined: Fri Aug 04, 2006 12:20 am
- Location: bedfordshire
Krish
for 50 m you have minimum 1 grab away
+£220
10 tonnes of type 1
+ £220
50 m of cheap blocks
+£500
4 tonnes of grit sand
+£120
7 bags of kiln dried sand
+ £28
kerbs?
steps?
recessed covers?
drainage?
wacker?
skip for additional rubbish?
it soon starts adding up,make sure you have costed it correctly before you start
LLL
for 50 m you have minimum 1 grab away
+£220
10 tonnes of type 1
+ £220
50 m of cheap blocks
+£500
4 tonnes of grit sand
+£120
7 bags of kiln dried sand
+ £28
kerbs?
steps?
recessed covers?
drainage?
wacker?
skip for additional rubbish?
it soon starts adding up,make sure you have costed it correctly before you start
LLL
-
- Posts: 1366
- Joined: Fri Apr 15, 2011 9:05 pm
- Location: Edinburgh
This.lutonlagerlout wrote:Krish
for 50 m you have minimum 1 grab away
+£220
10 tonnes of type 1
+ £220
50 m of cheap blocks
+£500
4 tonnes of grit sand
+£120
7 bags of kiln dried sand
+ £28
kerbs?
steps?
recessed covers?
drainage?
wacker?
skip for additional rubbish?
it soon starts adding up,make sure you have costed it correctly before you start
LLL
Was going to post a bunch of prices then realised it wasn't worth the effort.
When you get a few quotes they should all be in the same sort of region. When one is significantly cheaper they're going to take your money and run and or do a crap job. When one is significantly more expensive you're getting ripped off.
Care to guess which one the £2000 quote falls in to?