Hi again
Still doing my homework and am a bit unclear on the sub-base and how much mot to order. If I get it correctly the depth of the sub-base should be 100mm which should be filled with mot and compacted to level.
If so then if I had a 12 sqm area and I require a 100mm compacted sub-base then how many tonnes of MOT type 1 would be required? From what I can see on line 1 T does 12sqm to a depth of 50mm but I'm assuming this is before compacting?
Cheers
Monster
Sub-base depth
-
- Posts: 169
- Joined: Wed Nov 28, 2012 4:26 pm
- Location: Cambridgeshire
-
- Posts: 1366
- Joined: Fri Apr 15, 2011 9:05 pm
- Location: Edinburgh
Calculators
Calculator on that page has it at 2.4T
You don't get a tonne in a bulk bag either
Calculator on that page has it at 2.4T