Hi,

I cannot find any advice on the following issue.

I had the drive (140 m2) surface skimmed and 150mm DOT1 laid 2 years ago - to see what level of movement the cars produced. I got about 30mm rutting and tidal waves of DOT1 so I want to use cellular system.

Problem is the ground worker left the DOT1 at 150mm below the DPC with a fall away from the house.

It appears that I could set the drive to 75 mm below DPC if it has a gravel finish next to the wall.

Does this apply for a cellular system - its all gravel finish, sloping away from the house, fully drained by existing functional soakaways?

Cheers

Earl_H
Earl_H

lutonlagerlout
Site Admin
Posts: 15184
Joined: Fri Aug 04, 2006 12:20 am
Location: bedfordshire

Post: # 81274Post lutonlagerlout

you only want about 30 or so mm of gravel earl
what you have suggested sounds fine

LLL
"what,you want paying today??"

YOUR TEXT GOES HERE

Earl_H
Posts: 3
Joined: Sun Jul 29, 2012 3:23 pm
Location: Midlands

Post: # 81275Post Earl_H

Hi LLL

My post may have not been clear

Can I let the gravel surface get to 75mm below the DPC or do you propose 30mm below the DPC?

Cheers

Earl_H
Earl_H

lutonlagerlout
Site Admin
Posts: 15184
Joined: Fri Aug 04, 2006 12:20 am
Location: bedfordshire

Post: # 81284Post lutonlagerlout

our BCO will let 100mm go if it slopes away
plus with gravel you get less splash anyway
cheers LLL
"what,you want paying today??"

YOUR TEXT GOES HERE

Mikey_C
Posts: 952
Joined: Mon Oct 30, 2006 8:24 pm
Location: Bournemouth, Dorset

Post: # 81291Post Mikey_C

you only need 30mm OF GRAVEL, meaning if it was left 150mm short of dpc you will only 120mm below

Earl_H
Posts: 3
Joined: Sun Jul 29, 2012 3:23 pm
Location: Midlands

Post: # 81315Post Earl_H

Thanks Guys

The top of the MOT is 150mm from the DPC & the cell structure uses 35mm sharp sand and then 40mm for the cells (which are gravel filled) so I'm 25mm high.

I'll dig out and drop the level - doing the proper job.

???

Thanks again

Earl_H