Hi Guys,
Previously I have always laid all my edging course first, as I find this helps with providing a guide for my sand levels and screeding. And I am comfortable with using trammal bars for wider runs.
The project I am currently on is 51m long by 3.6m wide, which with 2 of us screeding is probably do-able between the edgings?
However, I have laid one run of edgings and I am paranoid that I will probably run in with my 2nd edging course leading to unwanted cuts.
I cant see a way of not putting the 2nd edging course in before I lay my blocks, but wondered if anyone had any ways that they would recommend I could try. I am fortunate that I do not have any levels (within reason) that I have to work to.
Also the blocks I am using are 80mm, I take it 50mm screed sand is still okay?
any advice welcomed!
Edging course last? - Edging course last
-
- Site Admin
- Posts: 15184
- Joined: Fri Aug 04, 2006 12:20 am
- Location: bedfordshire
russ the recommended sand has gone down to 30-40mm but i guess with 80 mm blocks you will be ok
I take it you must be doing 90 deg herringbone otherwise you wouldnt be worried about the cuts?
if you are that worried lay 18 blocks out ened to end and cut a piece of timber or ally as a profile 5 mm longer than that
as you lay your second edging use the profile to check alignement
better 5mm big than tight
doing edgings last is potentially a bodge
LLL
I take it you must be doing 90 deg herringbone otherwise you wouldnt be worried about the cuts?
if you are that worried lay 18 blocks out ened to end and cut a piece of timber or ally as a profile 5 mm longer than that
as you lay your second edging use the profile to check alignement
better 5mm big than tight
doing edgings last is potentially a bodge
LLL
-
- Posts: 1568
- Joined: Mon May 10, 2010 9:58 pm
- Location: Gatwick
- Contact:
-
- Posts: 2
- Joined: Thu Jul 05, 2012 9:49 pm
- Location: Coventry West Midlands
Yes will be a hering bone
Ok string line it is with timber spacer to be sure.
Always paranoid that I'm pulling the line sometimes with the odd block, especially on such a long run.
Found a few edgings that I laid today appeared to be off square to the line despite keeping them tight to the last. I spose I should always go to the line at all lengths
Thanks for the advice, there's never a short cut to doing a job correct!
Ok string line it is with timber spacer to be sure.
Always paranoid that I'm pulling the line sometimes with the odd block, especially on such a long run.
Found a few edgings that I laid today appeared to be off square to the line despite keeping them tight to the last. I spose I should always go to the line at all lengths
Thanks for the advice, there's never a short cut to doing a job correct!
-
- Posts: 1568
- Joined: Mon May 10, 2010 9:58 pm
- Location: Gatwick
- Contact:
-
- Site Admin
- Posts: 15184
- Joined: Fri Aug 04, 2006 12:20 am
- Location: bedfordshire
-
- Posts: 2598
- Joined: Wed Apr 08, 2009 8:01 am
- Location: Peoples Republic of Westhoughton
- Contact:
use a few steel road pins along the length and measure off the kerb to get the pins parallel, wrap your line round the pins making sure its taught and then use boning rods or bend down and eye the line through to get it to the correct position required
wrap insulation tape to the under side of the line so if it snaps or has to be taken off for any reason you know where to reposition it again
I have got balls of coloured line what must be 3 times the length you need to cover
wrap insulation tape to the under side of the line so if it snaps or has to be taken off for any reason you know where to reposition it again
I have got balls of coloured line what must be 3 times the length you need to cover
Crystalclear
Driveway and Patio Installer
Call us today
01942 840109
7 days a week 8am till 8pm
Driveways Patios and Paving Specialists
Driveways
Driveway and Patio Installer
Call us today
01942 840109
7 days a week 8am till 8pm
Driveways Patios and Paving Specialists
Driveways