Hi all
Just like to say this is a fantastic website !!!

I recently recieved a quote of £2175 to supply and fit 80mts of standard brindle majority of digging has been completed
Does this price sound right

I calculated
8 ton of MOT
8 ton of grit sand and the block to cover 80 meters

Cost for foundation would be approx £540


Any help is appreciated

Thanks
Aaron
aaron2788

local patios and driveway
Posts: 1568
Joined: Mon May 10, 2010 9:58 pm
Location: Gatwick
Contact:

Post: # 75474Post local patios and driveway

Get three quotes always. Seeing as the blocks will be about a grand, the sand and stone about 650.. I cant see anyone laying 80mtrs for a few hundred quid. Run a mile

haggistini
Posts: 1405
Joined: Thu Sep 27, 2007 10:29 am
Location: South Wales
Contact:

Post: # 75475Post haggistini

who was the quote from?
http://www.G-Tech.co
Bespoke Paving Contractor
M:07944036174

Less yap yap more tap tap!

aaron2788
Posts: 7
Joined: Sat Mar 17, 2012 12:55 pm
Location: Manchester

Post: # 75479Post aaron2788

I Got quote from a company based in Bolton...The qiote was £2175 supply and fit 30meters in Brindle..

My calculations are
3 Ton MOT
2 Ton Sand
3 pack of Brindle block
3 covers for Inspection Chambers

Cost for materials would be approx £550.00

Just seems to be quite exspenive for the labour if materials are only £550.00 unless this is a 2-3 week job

The ground is ready for MOT..So no digging required
aaron2788

local patios and driveway
Posts: 1568
Joined: Mon May 10, 2010 9:58 pm
Location: Gatwick
Contact:

Post: # 75485Post local patios and driveway

80 or 30, now im just confused if i was to price 30 it you would have to pay £1950 assuming no drainage or ic covers etc

aaron2788
Posts: 7
Joined: Sat Mar 17, 2012 12:55 pm
Location: Manchester

Post: # 75486Post aaron2788

Hi
Sorry for the confusion it is 30 meters if materials are £550 seems a lot for Labour ?? How long would this normally take? Yes there is 3 IC

Thanks mate
aaron2788

Carberry
Posts: 1366
Joined: Fri Apr 15, 2011 9:05 pm
Location: Edinburgh

Post: # 75489Post Carberry

9T of type one at 150mm - £270
2T of sharp sand - £60

3 packs of blocks - £300 (more if they are marshalls)
3 recessed covers - £150


That's 780, round up to £800 when you include kiln dried sand and cement.

That leaves 1375 for labour.

Sounds about right assuming they do a proper job.

Dave_L
Site Admin
Posts: 4732
Joined: Fri Jul 28, 2006 8:47 pm
Location: Somerset
Contact:

Post: # 75497Post Dave_L

Are these inset covers? If so there is a lot of work in fitting/cutting these in.
RW Gale Ltd - Civils & Surfacing Contractors based in Somerset

See what we get up to Our Facebook page

aaron2788
Posts: 7
Joined: Sat Mar 17, 2012 12:55 pm
Location: Manchester

Post: # 75499Post aaron2788

Carberry wrote:9T of type one at 150mm - £270
2T of sharp sand - £60

3 packs of blocks - £300 (more if they are marshalls)
3 recessed covers - £150


That's 780, round up to £800 when you include kiln dried sand and cement.

That leaves 1375 for labour.

Sounds about right assuming they do a proper job.
Hi Dave
I was under the impression I would need 2 inch mot as this is only a patio area...150 seems a lot for a patio
aaron2788

Carberry
Posts: 1366
Joined: Fri Apr 15, 2011 9:05 pm
Location: Edinburgh

Post: # 75500Post Carberry

aaron2788 wrote:
Carberry wrote:9T of type one at 150mm - £270
2T of sharp sand - £60

3 packs of blocks - £300 (more if they are marshalls)
3 recessed covers - £150


That's 780, round up to £800 when you include kiln dried sand and cement.

That leaves 1375 for labour.

Sounds about right assuming they do a proper job.

Hi Dave
I was under the impression I would need 2 inch mot as this is only a patio area...150 seems a lot for a patio
My mistake. that amount of MOT is for a driveway. for patio I would go 75mm minimum, so 4-5T.

ken
Posts: 274
Joined: Wed Feb 25, 2004 10:07 pm
Location: Leigh, Lancs

Post: # 75520Post ken

I live and work in the Manchester area, I’ve just worked out what id charge, and the price you have been given is spot on. And its a 2-3 day job, not 2-3 weeks.
Ken

KGC Block Paving

Leigh Lancashire

T:01942 601781 M:07989 376123