I'm laying a small patio (approx 2m x 3m) around a conservatory with 450x450 flags uniform thickness. My base will be 50mm MOT hardcore. From reading the information on this site I was thinking of laying the flags on a 50mm thick 10:1 sand/cement mix screed bed. I want to have 3mm joints between the flags as I don't want to have mortar joints.
I have some questions ???
1) As the area is small can I can compact without using a mechanical compactor and what should I use instead?
2) Can I lay all my screed out before laying or will the screed set before I finish (I will be working slowly as I'm a novice!)
3) What should I fill the joints in with. Can I use just kiln dried sand brushed in. Should I mix any cement in with the sand ?
Advice appreciated, thanks.
Dave
ps this is a great site.
Small patio laying - Advice needed
-
- Site Admin
- Posts: 8346
- Joined: Mon Jul 05, 2004 7:27 pm
- Location: Warrington, People's Republic of South Lancashire
- Contact:
1 - a punnel, the butt-end of a fence post, the head of sledge-hammer - anything that will hammer down the sub-base material and give good compaction.
2 - yes. Using a semi-dry mix will give you up to 6 hours working time at this time of year, so that's only 1m² per hour!
3 - kiln-dried sand. No cement necessary.
2 - yes. Using a semi-dry mix will give you up to 6 hours working time at this time of year, so that's only 1m² per hour!
3 - kiln-dried sand. No cement necessary.