Channels?ruts in driveway. i need help.

Setts and cobbles, tarmac, asphalt, resin systems, concrete whether it's plain, patterned or stencilled, gravels, etc.
Post Reply
ratgirl
Posts: 3
Joined: Mon Feb 28, 2005 7:30 pm
Location: essex

Post: # 7204Post ratgirl

HI anyone, July last year we had a gravel driveway done, but now it looks horrible there are ruts in it & the mud is coming through & there are big lumps in it along the ruts, (where it has channeled).The drive is 8x9 metres (72 square ft)
We have had the person round who done the driveway ( he is a friend of my dads, my dad used to work with him)anyway he reckons that he told my dad that he said not to use type 1 but to use limestone instead because it was better or to concrete it ( I have read the forum about concrete).
I asked my dad what it was dug out to.
It was dug out 6 inches (150mm) then filled with about 2 inches (50mm) at most of type 1 (I think it was about 10 ton) my dad said at this stage that it looked thin ( he told me tonight that he could still see the mud in some places) but the men who done it said it would be ok! Then they put gravel on top.the gravel is big stones not pea shingle ( I suppose they are about an inch round?)
Anyway both the men are coming back in the week to look at it, but my dad still says that they did not put enough type 1 down to start with.
The man said that type 1 doesn't go off (set) is this true?
Is there any difference between type 1 & limestone, which is better?
What do you think they would have to do to correct this?
Thanks to whoever reads this.
katie.

GaryN
Posts: 66
Joined: Mon Sep 29, 2003 4:07 pm
Location: Colchester, essex

Post: # 7205Post GaryN

Katie,
If they've dug out 150mm, and you still want the large gravel, in my opinion they would need to remove the gravel and lay and thoroughly compact approx. 110mm of Type 1. They should then lay the gravel to about 40mm depth and compact again.
I would personally use 10 or 14mm gravel and lay the gravel to a depth of 25mm. If you opt for this the type 1 would be 125mm deep.
Type 1 doesn't set but it does compact to a very solid base.
Type 1 can consist of crushed limestone. Did the 'base' which he put down have fines(dust)as well as solid pieces of stone?
Regards
Gary

ratgirl
Posts: 3
Joined: Mon Feb 28, 2005 7:30 pm
Location: essex

Post: # 7206Post ratgirl

Hi thanks for replying so quick, the stones that are down are 20mm, the 'base' was mostly 'dust' with some stone in but not a lot.
The mud is pushing the type 1 up.
The type 1 underneath is like mushy it hasnt gone hard.
Katie.

ratgirl
Posts: 3
Joined: Mon Feb 28, 2005 7:30 pm
Location: essex

Post: # 7207Post ratgirl

We will have to go for the first option, after compacting the gravel on the type 1, do we put more gravel on top?
My dad said that there is 5 yards of gravel on top.
Katie.

GaryN
Posts: 66
Joined: Mon Sep 29, 2003 4:07 pm
Location: Colchester, essex

Post: # 7215Post GaryN

Katie,
If you're going for 40mm depth of gravel I would spread a thin layer first, compact this and then add more gravel to the 40mm depth and compact again.
Regards
Gary

danensis
Posts: 335
Joined: Mon Aug 11, 2003 4:24 pm
Location: Derbyshire
Contact:

Post: # 7219Post danensis

My grandad used to say "Nivver have a gravel drive unless you've a servant to rake it ivery morning".