Hi me again!
Forgot to ask last time, I'm wondering what's the best way to tackle the sand bed. My current thinking is to have the 4 ton of sand delivered in jumbo bags and then spread, wack and screed managable areas of sand in sections.
I would then lay the blocks over this area before doing the same again on the next bit of sub base, rather than spread the whole 4 ton, wack it and then screed managable areas for laying.
My concern arises from the uncertainty over the weather in the next week or so, as I thought it would be better to protect the sand bed until I was ready to start laying the blocks.
Hope this makes sense
Steve
Preparing the sand bed
-
- Site Admin
- Posts: 8346
- Joined: Mon Jul 05, 2004 7:27 pm
- Location: Warrington, People's Republic of South Lancashire
- Contact:
-
- Posts: 5
- Joined: Fri Oct 01, 2004 8:00 pm
- Location: Pontefract